Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] May variance reports
- From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] May variance reports
- Date: Sun, 26 Jun 2022 15:38:35 +0100
Hello all,
-6.4.1 and 2 still nothing. Now one week past due, please get this done asap!
-6.5.3 is good now
-6.6.3: if you’re going to say substrates are going to be a year late, you should probably add a corrective action that says you’re trying to get a first batch much earlier. But in general I don’t recommend talking about a potential future bigger schedule variance to excuse a current schedule variance…
-6.6.4 is fine
-6.6.5 isn’t it time to put the LS3 delay in the schedule? The report is good.
-6.8 and 6.8.3: good, but "When
engineering resources become available they are put on project with an
effort rate higher than originally planned, with the goal of making up
schedule delays.” is really a corrective action, not an impact, so maybe make that move next month?
-6.10.2 is still missing
Thx
Gustaaf
On Jun 22, 2022, at 11:58 AM, Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu> wrote:
Hello all,
A friendly reminder that May variance reports are past due. A few comments:
-6.4.1 and 6.4.2 are missing
-6.5.3: the explanation doesn’t make sense to me: there’s a $100k positive cost variance, but the explanation says "PCB boards were late in arrival. This lead to a slower start to production then scheduled” which seems like a schedule variance explanation (and there is a small negative cost variance, but it’s not reportable).
-6.6.3/4/5 are missing
-6.8 and 6.8.2 are missing
-6.8.3 is fine. At some point somebody’s going to ask when the bleeding will stop…
-6.10.2 is missing.
Thanks!
Gustaaf
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] May variance reports,
Gustaaf Brooijmans, 06/22/2022
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] May variance reports, Gustaaf Brooijmans, 06/26/2022
Archive powered by MHonArc 2.6.24.