Hello all,

A friendly reminder that VRs for October are due. Here are some comments on
those that have been posted:

6.4.1 looks good to me. (For future reference 0.5 is the SPI, the SV is
$2.1M)
==> please submit this!

6.5.3 looks fine as well
==> please submit this!

6.6: CA: the supply chain change should be made as part of the rebaseline BCP
=> I unlocked this
6.6.1: is the readout card delay due to supply chain or other delays?
=> I unlocked this
6.6.3 looks good
=> please submit this!
6.6.4: "We expect to be ready for preproduction in August/September”? For
the CA, see above (will be part of rebaseline)
=> I unlocked this as well.

Thanks,

Gustaaf