  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] October VRs
  • Date: Tue, 22 Nov 2022 13:56:40 -0500


Hello all,

Today’s update:

6.4, 6.4.2 are still missing

6.4.1 and 6.4.3 I have approved
6.6.1, 6.6.3 and 6.6.4 I’ll approve. (Although for 6.6.4 I don’t understand
why you refer to August/September as if it’s in the future, when this must be
2022…)

6.8 and 6.8.4 are still missing
6.8.3 I’ll approve

Best,

Gustaaf

> On Nov 21, 2022, at 10:58 AM, Gustaaf Brooijmans
> <gusbroo AT nevis.columbia.edu> wrote:
>
>
> Hello all,
>
> An update:
>
> 6.4, 6.4.2 and 6.4.3 are missing
> 6.4.1 is not submitted
>
> 6.5.3: thanks for submitting, I have approved
>
> 6.6 thanks for the update
> 6.6.1: thanks for the update, please submit this
> 6.6.3: please submit
>
> 6.6.4 still needs updating? Or are you talking about August/September of
> 2023 for the 10 boards? The CA now says: "possible on the 10 boards we can
> produce with the LDO's on hand. The order for these LDO chips has already
> been placed (expect shipment in March/April 2023).” If they are on hand,
> why do you need to place the order? If this is for the rest of the LDOs,
> it seems to clash with the impact statement "Unfortunately, we will not be
> able to produce the rest of preproduction boards until more LDO chips are
> available - which are currently out-of-stock with a 12 month lead time”
> => I have unlocked this
>
> 6.6.5 I have approved
>
> 6.8.* are missing
>
> Please complete this before the holiday.
>
> Thx
>
> Gustaaf
>
>
>> On Nov 18, 2022, at 9:49 AM, Gustaaf Brooijmans
>> <gusbroo AT nevis.columbia.edu> wrote:
>>
>>
>> Hello all,
>>
>> A friendly reminder that VRs for October are due. Here are some comments
>> on those that have been posted:
>>
>> 6.4.1 looks good to me. (For future reference 0.5 is the SPI, the SV is
>> $2.1M)
>> ==> please submit this!
>>
>> 6.5.3 looks fine as well
>> ==> please submit this!
>>
>> 6.6: CA: the supply chain change should be made as part of the rebaseline
>> BCP
>> => I unlocked this
>> 6.6.1: is the readout card delay due to supply chain or other delays?
>> => I unlocked this
>> 6.6.3 looks good
>> => please submit this!
>> 6.6.4: "We expect to be ready for preproduction in August/September”? For
>> the CA, see above (will be part of rebaseline)
>> => I unlocked this as well.
>>
>> Thanks,
>>
>> Gustaaf
>>
>>
>> _______________________________________________
>> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
>>
>
> _______________________________________________
> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
>