Hello all,
January VRs are due. Here are comments on the ones that have been entered
(thanks!).
Best,
Gustaafd
-6.4 is missing
-6.4.1: it is the CPI that’s 0.57, not the SV. "The increase from $294k to
$419k” should that be to $477k? Maybe the CA should add that the VL+
purchase date will be moved as part of the rebaseline? I’ll unlock this.
-6.4.2/3 are missing
-6.5.3 looks good.
-6.5.4 is missing
-6.6 looks good
-6.6.1 looks good
-6.6.3 is fine (although one has to read between the lines to get the actual
explanation)
-6.6.4: for the cost variance, you now list complexity. What is the
contribution of complexity to this? I’ll unlock.
-6.6.5 looks good
-6.8 is missing
-6.8.3: looks good. This continues to lose ground… will the future schedule
(post-BCP-1057) be realistic?
-6.8.4 is missing
-6.10.2 is missing
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] January VRs,
Gustaaf Brooijmans, 02/20/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] January VRs,
Gustaaf Brooijmans, 02/24/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] January VRs, Gustaaf Brooijmans, 02/26/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] January VRs,
Gustaaf Brooijmans, 02/24/2023
Archive powered by MHonArc 2.6.24.