[Usatlas-hllhc-l2deputymgmt-nsf-l] Bug fixes for NSF rebaseline review
- From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
- Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] Bug fixes for NSF rebaseline review
- Date: Tue, 7 Mar 2023 19:06:57 +0100
Hello all,
I know that there were some bug fixes needed for the NSF rebaseline review
(eg some updated quotes where the new amount didn’t make it into P6). Please
send these fixes to the PO asap, as the deadline to post for the review is
late March and we would need to get the fixes in and re-run the cost books.
Thanks,
Gustaaf