usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions
- From: Michael Tuts <tuts AT pmtuts.net>
- To: Thomas Schwarz <schwarzt AT umich.edu>, Stephanie Majewski <smajewsk AT uoregon.edu>
- Cc: "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions
- Date: Fri, 3 Mar 2023 14:40:20 +0000
Hi Tom,
Thanks. I will pass on the first comment since that clarifies the need-by-date and it is in the comments section. The second point you made is perhaps suggesting a change to a recommendation which also includes an “either … or”, so what you have written is really a response to the recommendation. We should not try to change a committee recommendation, that is the committee’s prerogative so I won’t send the comment to them, but you can certainly put it in a future response to the recommendation.
Cheers, Mike
From: Thomas Schwarz <schwarzt AT umich.edu>
Hi Mike,
Here are a couple responses that I think clarify a few misunderstandings. I also attached the .doc with the comments in-line.
Thanks, Tom
Muon Comments: ● The CSM sub-project: without urgently addressing the problem with the commercial part availability (that is either unavailable or in limited supply or available elsewhere at higher cost), the project runs a sizable risk of missing the need-by-date. Since this specific ATLAS need-by date is connected with the chamber installation planning, the impact of failing the need-by dates can be significant. A good use of contingency could be to advance this purchase to mitigate this risk, as additional wait time will also add to the standing army costs in addition to schedule risk.
The above is probably coming from a misunderstanding on delivery dates. Sorry, I don’t think I explained that very well during our breakout. There are two dates of importance. (1) “off-detector” which requires about 100 CSM to be mounted on the sMDT before they are installed - this is where the 170 wd of float sits, and (2) “on-detector” which are mounted directly on chambers inside the detector - this has a much longer float. Preproduction for the CSM will produce enough boards to satisfy the “off-detector” requirements, so it’s not so tight.
Muon Recommendations: ● The project should consider the possibility to either update the CSM design with parts that are currently available on the market and are radiation hard or urgently secure the parts that the design critically depends on (a specific voltage regulator) to mitigate the risk of not meeting the ATLAS deadline. The project should reach a decision by the next annual review, and should be prepared for discussing the progress at the rebaselining review.
There actually are currently no LDO’s on the market that have been tested as radiation hard, and meet our specifications, other than the part we have chosen. Many have been tested for radiation but have failed. This would likely cause more delay/cost than either waiting out the components, or as you suggest, just purchasing at the higher price. Note that purchasing at the current price would require an additional $100k cost – which could be worth it given the timescales involved.
Thank you for all the help in the review! We very much appreciate it! The feedback is exactly what we needed.
Tom (on behalf of muon team)
=================== Tom Schwarz Associate Professor Department of Physics University of Michigan Office: 734-764-8941 Lab: 734-763-7805 ===================
On Thu, Mar 2, 2023 at 1:23 PM Thomas Schwarz <schwarzt AT umich.edu> wrote:
|
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions
, (continued)
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, Michael Tuts, 03/02/2023
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] FW: March 1-2 Director’s Review Homework Questions,
Michael Tuts, 03/02/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: March 1-2 Director’s Review Homework Questions, John Parsons, 03/02/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: March 1-2 Director’s Review Homework Questions, Mark Oreglia, 03/02/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
Stephanie Majewski, 03/02/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
Thomas Schwarz, 03/02/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
Thomas Schwarz, 03/02/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
Gustaaf Brooijmans, 03/02/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
Thomas Schwarz, 03/02/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, Gustaaf Brooijmans, 03/03/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
Thomas Schwarz, 03/02/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, Michael Tuts, 03/03/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
Gustaaf Brooijmans, 03/02/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
Thomas Schwarz, 03/02/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
Thomas Schwarz, 03/02/2023
Archive powered by MHonArc 2.6.24.