Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - [Usatlas-hllhc-l2deputymgmt-nsf-l] One more day before going public with the review website...

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Michael Tuts <tuts AT pmtuts.net>
  • To: "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Cc: "Smith, Rosemarie" <rsmith2 AT bnl.gov>
  • Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] One more day before going public with the review website...
  • Date: Tue, 28 Mar 2023 17:41:53 +0000

Hi All,

 

In communicating with Mark Coles, he asked for a summary of the PEP changes. I produced such a summary (and hinted that another option to make it perhaps clearer to the committee and internally at NSF would be to have a listing of side-by-side before-and-after changes – I originally sent him a set of changes that referenced the old PEP page numbers  and had a snippet of the change from the updated PEP). Turns out he very much wanted this other option that I told him would take another day… hence the new delay until tomorrow before we send the weblink to NSF and the reviewers. More time to cross check. If you are interested in the PEP changes I include the original summary file I sent to Mark – attached.

 

So, the current plan is to go live tomorrow. Please upload talks to DocDB and let Rosemarie know the new DocDB# so she can add the links in the indico.

 

Cheers, Mike

Attachment: Summary of Changes to PEP for Rebaseline 2023.docx
Description: Summary of Changes to PEP for Rebaseline 2023.docx