usatlas-hllhc-l2deputymgmt-nsf-l - [Usatlas-hllhc-l2deputymgmt-nsf-l] Fwd: [External] Action Items from NSF I&I meeting

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: "Evans, Harold G." <hgevans AT indiana.edu>
  • To: "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] Fwd: [External] Action Items from NSF I&I meeting
  • Date: Mon, 3 Jul 2023 12:10:35 +0000

Hi all,

Just a quick reminder to please get the information requested below to me by COB today.

Thanks  -  Hal

-------- Forwarded Message --------
From: "Evans, Harold G." <hgevans AT indiana.edu>
To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
Subject: [External] [Usatlas-hllhc-l2deputymgmt-nsf-l] Action Items from NSF I&I meeting
Date: Thu, 29 Jun 2023 19:11:22 +0000

This message was sent from a non-IU address. Please exercise caution when clicking links or opening attachments from external sources.

Hi all,

Thanks for the productive discussion at today's NSF L2 meeting. Here is my take on the action items that came out of the meeting. I will need input on all of these byMonday, July 3 at the latest so that I can construct an effective argument for the scubbing.

0. Everyone: look at the docs linked below and point out any errors that I've made in interpreting your data.

1. Everyone: add uncosted effort estimates under the new assumption/policy that any institute receiving I&I funding should also provide a commensurate level of uncosted student and/or postdoc effort.

2. Everyone: add a reasonable level of travel to your I&I estimate

3. Muon: reduce the total request to around $3M

4. LAr: justify the need for expert support in the gap period in terms of what these people would do during that period that would be of benefit to M&O. It will probably also be necessary to reduce the total expert request

5. Trigger: quantify the expected need for gap support of algorithm experts in FY28. Provide some explanation of what the supported individuals would do for M&O.

The documents I showed during the meeting are linked below.
    - spreadsheet
    - graphical schedule overview

Thanks  -  Hal
-- 
------------------------------------------------------------------------------
 Hal Evans                        hgevans AT indiana.edu
           http://hgevans.pages.iu.edu/
 Tel: (812)856-3828                    Fax: (812)855-5533
 204 Swain Hall West               Indiana University
 727 E. Third St.                Bloomington, IN 47405
------------------------------------------------------------------------------
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l

-- 
------------------------------------------------------------------------------
 Hal Evans                        hgevans AT indiana.edu
           http://hgevans.pages.iu.edu/
 Tel: (812)856-3828                    Fax: (812)855-5533
 204 Swain Hall West               Indiana University
 727 E. Third St.                Bloomington, IN 47405
------------------------------------------------------------------------------


  • [Usatlas-hllhc-l2deputymgmt-nsf-l] Fwd: [External] Action Items from NSF I&I meeting, Evans, Harold G., 07/03/2023

Archive powered by MHonArc 2.6.24.

Top of Page