Hi all,
Thanks for your feedback on the NSF I&I risks. A couple of things have emerged from what you've sent me.
1. We should think carefully about the probability of any new or modified "no enhanced surface integration" risks. Presumably, the probability of these new/modified risks occurring should be quite high since the assumption behind them is that we're *not*
doing the surface integration. Even a 100% probability would not be unreasonable - but I'll leave it to you to determine the actual value that best fits your risk.
2. It's very important to include an explanation of how you calculated the impacts for these new/modified risks. I will have to defend these estimates at the Ops review, but won't be able to do so if I don't have any background information.
Let's aim for Monday next week (Aug. 26) to collect the updated risks. Let me know if this is not feasible for you.
Thanks - Hal
--
------------------------------------------------------ Hal Evans hgevans AT iu.edu Professor of Physics http://hgevans.pages.iu.edu/ Tel: (812)856-3828 Fax: (812)855-5533 253 Swain Hall West Indiana University 727 E. Third St. Bloomington, IN 47405 ------------------------------------------------------
-
[[Usatlas-hllhc-l2deputymgmt-nsf-l] ] thoughts on NSF I&I risk estimates,
Evans, Harold G., 08/23/2024
- Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] [External] thoughts on NSF I&I risk estimates, Evans, Harold G., 08/26/2024
Archive powered by MHonArc 2.6.24.