Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] I&I Risk Register and Impact Statement

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: "Evans, Harold G." <hgevans AT iu.edu>
  • Cc: "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>, "Christopher.Bee AT stonybrook.edu" <Christopher.Bee AT stonybrook.edu>, "schwier AT msu.edu" <schwier AT msu.edu>, "torrence AT uoregon.edu" <torrence AT uoregon.edu>, "morii AT g.harvard.edu" <morii AT g.harvard.edu>, Srini Rajagopalan <srinir AT bnl.gov>
  • Subject: Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] I&I Risk Register and Impact Statement
  • Date: Thu, 29 Aug 2024 14:22:48 +0200


Hi Hal,

I had to make a copy to be able to add suggested edits and comments.  This can be found at 


Best,

Gustaaf


On Aug 28, 2024, at 18:53, Evans, Harold G. <hgevans AT iu.edu> wrote:

Hi all,

I've uploaded the latest version of the I&I Risk Register to docdb #196 (review/p2-lhc). I only changed the "IIC risk register" entry. The "Standard" and "Supply chain" registers remain the same as before.

I've also edited all of the Impact Statements that you sent to make them more conistent with each other and merged them into a single document:
Please have a look and let me know if I've messed anything up. We may want to post this in the docdb at some point, but that can wait.

Finally, I've incorporated the comments that you sent me on my presentation (thanks!). I'll upload it to the Review Rehearsal indico page later this afternoon.
    access: ReviewRehearsal

Best  -  Hal


On Tue, 2024-08-27 at 12:37 -0400, Hal Evans wrote:
Hi all,

Thanks for all of your inputs! I'm attaching a first draft of the I&I talk for the upcoming Ops Review. I will be presenting this at the review rehearsal on Thursday this week, so please have a look and send me any quick feedback you might have before then. Of course, I'm happy to accept suggestions after Thursday as well.

If you'd like to sit in on the rehearsal (1:00 pm EDT on 8/29), the indico page is given below:
    access: ReviewRehearsal
Srini/Chris: I assume that it's ok for the HL-LHC L2s to join if they can?

An important part of the presentation will focus on I&I risks. I'm also attaching the updated I&I Risk Register. Note that I've modified the probabilities of all risks related to "No Enhanced Surface Testing" to be 100%. These risks are used to indicate the impact on the project if we are not able to exercise the enhanced testing scope opportunities, so - by construction - they will be realized under that assumption. Unless I hear any objections, I'll upload this new version to the docdb tomorrow.

I'm still working on merging all your individual Impact Statements for the "No Enhanced Surface Testing" risks. This should be ready in a day or two. I'll circulate it as soon as it's available.

Thanks  -  Hal



-- 
------------------------------------------------------
 Hal Evans                             hgevans AT iu.edu
               Professor of Physics
           http://hgevans.pages.iu.edu/
 Tel: (812)856-3828                Fax: (812)855-5533
 253 Swain Hall West               Indiana University
 727 E. Third St.               Bloomington, IN 47405
------------------------------------------------------