- From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- To: usatlas-hllhc-l2deputymgmt-nsf-l <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Cc: Tim Andeen <timothy.robert.andeen AT cern.ch>, Andy Haas <andy.haas AT nyu.edu>, Haleh Hadavand <hadavand AT uta.edu>, Junjie Zhu <junjie AT umich.edu>, Thomas Schwarz <schwarzt AT umich.edu>
- Subject: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] August VRs
- Date: Sun, 21 Sep 2025 11:17:40 -0400
!-------------------------------------------------------------------|
This Message Is From an External Sender
This message came from outside your organization.
|-------------------------------------------------------------------!
Hello all,
A friendly reminder that August VRs are due - thanks to all who have already
submitted. Below are my comments on what’s there.
Best,
Gustaaf
-6.4: looks good, please submit it.
-6.4.1: you say “we have received all VTRx+ devices at CERN.” Is that
accurate? It seems to conflict with what’s written for 6.4. (I think you
can just remove that sentence, since it has little to do with the direct
impact.) I have unlocked this.
-6.4.3: You are only asked for a report on cost variance, so please don’t
write about schedule variance. (Didn’t need to unlock as wasn’t submitted)
-6.5.4 I have approved. Next time, please add something in the impact
statement about available float.
-6.6.3 is missing
-6.6.4: the cost variance number in the text is $11k different from the
actual number. I’ve unlocked this.
-6.8.1 and 6.8.4 I’ve approved
-
[[Usatlas-hllhc-l2deputymgmt-nsf-l] ] August VRs,
Gustaaf Brooijmans, 09/21/2025
-
Message not available
-
Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] August VRs,
Gustaaf Brooijmans, 09/22/2025
- Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] August VRs, Gustaaf Brooijmans, 09/23/2025
-
Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] August VRs,
Gustaaf Brooijmans, 09/22/2025
-
Message not available
Archive powered by MHonArc 2.6.24.