Hi John and all,
I put a draft of my slides for pre-FDR here:
I need to upload them to docdb for the reviewers on Tuesday I think. Any comments would be appreciated.
I just started with the PDR slides and added John's PDR slides on for the technical overview and physics flowdown (which I think is in my talk this time, slides 4-21). If you recall, we included some duplication of material in the slides at PDR (really 3 separate talks) because the review was in three parts. This is not the case anymore, but for the most part the extra slides makes it easier to follow some parts, so I left some of them in.
Slide 10 - didn't update science flowdown chart
Slides 19/20 - should I talk about the DOE/NSF scope or will you do that John?
Generally: Did not removing lpGBT info, but will not be focus of review.
Slide 44- Added QA/QC slide
Slide 58 - I don't have a nice updated schedule (maybe no changes at this level)
Slide 62 - Same as slide 64
Slide 65 - No change in Uncert. Categories
Slide 67/68 - No change to risks (checked Jan 2019 risk xls in docdb).
I'm not sure where Milestones go, but I don't have an update for that either.
I still need to refresh the backup slides on the lpGBT (86-90).
Best, Tim