usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] schedule performance validation reports
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] schedule performance validation reports
- Date: Mon, 13 May 2019 14:35:04 -0400
An urgent request from Penka. I attach the LAr file,
which I got out of docdb. Please check your L3
section right away and let me know any issues.
John
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] schedule performance validation
reports
Date: Mon, 13 May 2019 17:48:51 +0000
From: Novakova, Penka N <penka AT bnl.gov>
To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
CC: OConnor, Jennifer <jennifer AT bnl.gov>
Dear All,
We are now implementing the second step in the monthly statussing process – validation of the monthly status.
The performance validation reports have been uploaded to docdb 770.
Please review the report for your system/control account.
Here are the things you need to pay attention to
1. Is the **percent complete** correct?
2. Are the completed activities entered into P6 as expected?
3. Is the **expected finish** date (if you have provided on) correct?
The reports are really short so we expect that you will be able to review and provide feedback by 10am eastern tomorrow morning.
After that time we will be integrating the status into Cobra to generate the April CPR.
Thank you very much in advance.
Penka for the project controls team
P.S. FYI **BL Start** is the Baseline start or the start date in the master schedule. **WS Start** is the working schedule start or actual start date. The vertical blue line in the Gantt chart represents the reporting period cutoff date in the schedule (April 30, 2019).
_______________________________________________
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l
Attachment:
AP2 6.04 LAr Performance Verification.pdf
Description: Adobe PDF document
- [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] schedule performance validation reports, John Parsons, 05/13/2019
Archive powered by MHonArc 2.6.24.