usatlas-hllhc-lartl2l3-l - Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] July status sheets

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: "Ma, Hong" <hma AT bnl.gov>
  • To: "Parsons, John" <parsons AT nevis.columbia.edu>, Tim Andeen <timothy.robert.andeen AT cern.ch>
  • Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] July status sheets
  • Date: Sun, 4 Aug 2019 20:30:23 +0000

 

                Completed for 6.4.5. 

                For preprototype3 shipping to Columbia (which was left not started before) , I filled it as it was completed in April, since LAUROC1 was shipped to Columbia.

 

I will check if Hao is back or not tomorrow.

 

                Hong.

 

From: Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>
Date: Saturday, August 3, 2019 at 10:06 PM
To: Tim Andeen <timothy.robert.andeen AT cern.ch>
Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] July status sheets

 

 

Thanks Tim.

 

On 8/3/19 9:58 PM, Tim Andeen wrote:

Done, including some clean up from missed tasks due to the RLS changes. -tim

On Sat, Aug 3, 2019 at 11:47 AM John Parsons <parsons AT nevis.columbia.edu

     A reminder that the July status was due on Thursday,

     so please take care of it asap.  So far I have heard

     only from Andy.

                      John

     On 7/29/19 4:40 PM, John Parsons wrote:

      >

      > Hi all,

      >

      >      It is monthly statusing time again.  Please fill out

      > your L3 part by the end of Thursday at the latest, and let

      > me know when you are done.  This should not take more than

      > 10-15 minutes of your time, so please make time to do it

      > asap (despite the ongoing NSF DR).

      >      Thanks,

      >          John

      >

      > -------- Forwarded Message --------

      > Subject:     [Usatlas-hllhc-l2l3ics-l] July status sheets

      > Date:     Mon, 29 Jul 2019 19:55:54 +0000

      > From:     Novakova, Penka N <penka AT bnl.gov <mailto:penka AT bnl.gov>>

      >

      >

      >

      > Dear All,

      >

      > *If you need help pleaseDO NOT replay to the mailing list*

      >

      > The status sheets for the month of July are now available in

     google docs

      >

      >    * 6.01 – Pixels -

      >

      >

      >    * 6.02 – Strips -

      >

      >

      >    * 6.03 – Global Mechanics -

      >

      >

      >    * 6.04 – LAr -

      >

      >

      >    * 6.05 – Tile -

      >

      >

      >    * 6.06 – Muon -

      >

      >

      >    * 6.07 – DAQ -

      >

      >

      >    * 6.08 – Trigger -

      >

      >

      >

      > We have included the schedule changes for Pixel, Strips and GM in

     this

      > month’s status sheets.

      >

      > Please remember to update the status online – DO NOT download the

     files.

      >

      > The reports are at L2. The reports contain activities for July

      > 2019-September 2020 in case some activities have started earlier.

     You

      > can filter for your CAM name in column D.

      >

      > Please provide status in columns L, M, N, and O. Make sure that you

      > enter the actual start date for all started activities and finish

     date

      > for all activities that are 100% completed, this information is

     crucial

      > when we update the schedule in P6. If the activity is completed

     but you

      > do not remember the exact start and finish dates you can enter

     your best

      > estimate or copy the dates from the baseline start and finish

     dates (BL

      > Project Start/BL Project Finish). Do NOT enter dates after July

     31, 2019

      > in actual start/finish dates (columns M and N) , this creates

     errors in

      > P6. Also do not write any notes in the spreadsheet, we may add a

     column

      > for comments in the future.

      >

      > Please complete the July status update by Monday, August 5.

      >

      > We expect that the L2 managers and deputies will notify us (Penka,

      > Heidi, Carrie, Jenn) as soon as the status for their system is

     complete.

      >

      > Let us know if you have any questions or comments/suggestions to

     make

      > the process smoother and more user-friendly.

      >

      > Thank you!

      >

      > Penka for the project controls team

      >

      > Penka Novakova

      >

      > U.S. ATLAS HL-LHC Project Office

      >

      > Bldg. 510

      >

      > Brookhaven National Lab

      >

      > Upton, NY 11973

      >

      > Tel. 631-344-2502

      >

      >

      > _______________________________________________

      > Usatlas-hllhc-lartl2l3-l mailing list

      >

     --

     ______________________________________________________________________

     John Parsons

     Nevis Labs,             Email: parsons AT nevis.columbia.edu

        Columbia University   Phone: (914) 591-2820

     P.O. Box 137            Fax: (914) 591-8120

     Irvington, NY 10533     WWW:

     ______________________________________________________________________

     _______________________________________________

     Usatlas-hllhc-lartl2l3-l mailing list

--

---------------

Tim Andeen

Assistant Professor, Department of Physics

College of Natural Sciences

The University of Texas at Austin

Austin, TX 78712-1192

web: tandeen.web.cern.ch <http://tandeen.web.cern.ch>

office (TX): PMA 10.208

office (CERN): 304/1-024

ph (TX):  +1 512 475-9575

ph (CERN): +41 (0)22 76 758 14

---------------

 

--

______________________________________________________________________

 

John Parsons

Nevis Labs,                          Email: parsons AT nevis.columbia.edu

  Columbia University      Phone: (914) 591-2820

P.O. Box 137                       Fax: (914) 591-8120

 

______________________________________________________________________

_______________________________________________

Usatlas-hllhc-lartl2l3-l mailing list




Archive powered by MHonArc 2.6.24.

Top of Page