Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] July status sheets

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "Ma, Hong" <hma AT bnl.gov>, Tim Andeen <timothy.robert.andeen AT cern.ch>
  • Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] July status sheets
  • Date: Sun, 4 Aug 2019 17:01:27 -0400


OK, thanks.

On 8/4/19 4:30 PM, Ma, Hong wrote:
                Completed for 6.4.5.

                For preprototype3 shipping to Columbia (which was left not started before) , I filled it as it was completed in April, since LAUROC1 was shipped to Columbia.

I will check if Hao is back or not tomorrow.

                Hong.

*From: *Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>
*Date: *Saturday, August 3, 2019 at 10:06 PM
*To: *Tim Andeen <timothy.robert.andeen AT cern.ch>
*Cc: *"usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
*Subject: *Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] July status sheets

Thanks Tim.

On 8/3/19 9:58 PM, Tim Andeen wrote:

Done, including some clean up from missed tasks due to the RLS
changes. -tim

On Sat, Aug 3, 2019 at 11:47 AM John Parsons
<parsons AT nevis.columbia.edu <mailto:parsons AT nevis.columbia.edu>

<mailto:parsons AT nevis.columbia.edu>
<mailto:parsons AT nevis.columbia.edu%3e>> wrote:

     A reminder that the July status was due on Thursday,

     so please take care of it asap.  So far I have heard

     only from Andy.

                      John

     On 7/29/19 4:40 PM, John Parsons wrote:

      >

      > Hi all,

      >

      >      It is monthly statusing time again.  Please fill out

      > your L3 part by the end of Thursday at the latest, and let

      > me know when you are done.  This should not take more than

      > 10-15 minutes of your time, so please make time to do it

      > asap (despite the ongoing NSF DR).

      >      Thanks,

      >          John

      >

      > -------- Forwarded Message --------

      > Subject:     [Usatlas-hllhc-l2l3ics-l] July status sheets

      > Date:     Mon, 29 Jul 2019 19:55:54 +0000

      > From:     Novakova, Penka N <penka AT bnl.gov
<mailto:penka AT bnl.gov> <mailto:penka AT bnl.gov> <mailto:penka AT bnl.gov%3e>>

      > To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
<mailto:usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>

     <mailto:usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>

      > <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
<mailto:usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>

     <mailto:usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
<mailto:usatlas-hllhc-l2l3ics-l AT lists.bnl.gov%3e>>

      >

      >

      >

      > Dear All,

      >

      > *If you need help pleaseDO NOT replay to the mailing list*

      >

      > The status sheets for the month of July are now available in

     google docs

      >

      >    * 6.01 – Pixels -

      >

      >


https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1PooqGexr9flX9QAIoWdEBN9GLh7j8x735k771DxxGdk_edit-3Fusp-3Dsharing&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=oPbdxIi5S33bnqSmxX8AFZuAoTHi9zdoehAy76WFmlc&s=79fowlaUmvYhso9U7KAPWmswFs13mrND7txKPrSkuU4&e=

      >    * 6.02 – Strips -

      >

      >


https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1WGgBM-5Fa1aGajgXMOuKsRDiyVKlBGHHtvj3p4Mrs-5F7g0_edit-3Fusp-3Dsharing&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=oPbdxIi5S33bnqSmxX8AFZuAoTHi9zdoehAy76WFmlc&s=9gtHNSEzQcUnk6pLJHW9dbPl0KN3qm6NKdeFDpcHuPE&e=

      >    * 6.03 – Global Mechanics -

      >

      >


https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1-5FcOezr6BTPDk-2D9RvGUQB9ehXmalFN5KURkxThwdFkq4_edit-3Fusp-3Dsharing&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=oPbdxIi5S33bnqSmxX8AFZuAoTHi9zdoehAy76WFmlc&s=6UPXyEMhqjH-UQT8JqlCHrNWwT3m0Z6XIveIYXEdvYg&e=

      >    * 6.04 – LAr -

      >

      >


https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1xqRZJS6NiA00Il6kHiHJQ6oo3MzwKeIg9xiQCZZxCck_edit-3Fusp-3Dsharing&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=oPbdxIi5S33bnqSmxX8AFZuAoTHi9zdoehAy76WFmlc&s=BuRvOcifRVXY5v8p5UYC7GKhkqFhphNWZkZaZYoiR9g&e=

      >    * 6.05 – Tile -

      >

      >


https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1Vm9dHz7VdJbwM5UkySM64-2D-5FJiAWutcHhekRHuF0Q4gk_edit-3Fusp-3Dsharing&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=oPbdxIi5S33bnqSmxX8AFZuAoTHi9zdoehAy76WFmlc&s=yXKdW-YNziF5Ojvg7APK8igf7bvjAED38hllhTghnug&e=

      >    * 6.06 – Muon -

      >

      >


https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_14j5CBnLa0ZKQUHoOov9v03f9UkX28QFbP3W3vLGIRK0_edit-3Fusp-3Dsharing&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=oPbdxIi5S33bnqSmxX8AFZuAoTHi9zdoehAy76WFmlc&s=z5aFdq6jYhlCiIuKEk9HIbsV5jag9sZofTdY698JoFw&e=

      >    * 6.07 – DAQ -

      >

      >


https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1ptbhPJmgoAbOpQWRPLTs7tWP1G4Kh-5FADvCRwKT7PXsM_edit-3Fusp-3Dsharing&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=oPbdxIi5S33bnqSmxX8AFZuAoTHi9zdoehAy76WFmlc&s=KNgQ4eQ349wUJGUTKFVUcj1OHbngv9OrJXA6QK2qNbE&e=

      >    * 6.08 – Trigger -

      >

      >


https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1qA2KuAS5qwbxKFP211SG-5FuYQZEz7DA33fgmyQWpTWyU_edit-3Fusp-3Dsharing&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=oPbdxIi5S33bnqSmxX8AFZuAoTHi9zdoehAy76WFmlc&s=MjWChbPi5ISRjkeFMVTjspI7RH44IRMpsc2JsJ3YjdU&e=

      >

      > We have included the schedule changes for Pixel, Strips and
GM in

     this

      > month’s status sheets.

      >

      > Please remember to update the status online – DO NOT
download the

     files.

      >

      > The reports are at L2. The reports contain activities for July

      > 2019-September 2020 in case some activities have started
earlier.

     You

      > can filter for your CAM name in column D.

      >

      > Please provide status in columns L, M, N, and O. Make sure
that you

      > enter the actual start date for all started activities and
finish

     date

      > for all activities that are 100% completed, this information is

     crucial

      > when we update the schedule in P6. If the activity is completed

     but you

      > do not remember the exact start and finish dates you can enter

     your best

      > estimate or copy the dates from the baseline start and finish

     dates (BL

      > Project Start/BL Project Finish). Do NOT enter dates after July

     31, 2019

      > in actual start/finish dates (columns M and N) , this creates

     errors in

      > P6. Also do not write any notes in the spreadsheet, we may
add a

     column

      > for comments in the future.

      >

      > Please complete the July status update by Monday, August 5.

      >

      > We expect that the L2 managers and deputies will notify us
(Penka,

      > Heidi, Carrie, Jenn) as soon as the status for their system is

     complete.

      >

      > Let us know if you have any questions or
comments/suggestions to

     make

      > the process smoother and more user-friendly.

      >

      > Thank you!

      >

      > Penka for the project controls team

      >

      > Penka Novakova

      >

      > U.S. ATLAS HL-LHC Project Office

      >

      > Bldg. 510

      >

      > Brookhaven National Lab

      >

      > Upton, NY 11973

      >

      > Tel. 631-344-2502

      >

      >

      > _______________________________________________

      > Usatlas-hllhc-lartl2l3-l mailing list

      > Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
<mailto:Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>

     <mailto:Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>

      > https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l

      >

     --

______________________________________________________________________

     John Parsons

     Nevis Labs,             Email: parsons AT nevis.columbia.edu
<mailto:parsons AT nevis.columbia.edu>

     <mailto:parsons AT nevis.columbia.edu>

        Columbia University   Phone: (914) 591-2820

     P.O. Box 137            Fax: (914) 591-8120

     Irvington, NY 10533     WWW:


https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=dBF02P_fWftPwJn6F5L67DDW5hfBPX2uK7iPVBBfHJk&s=e1u-rnymQF7fVHd7oN6g1WMnf99bM_u1YzOjwy95x00&e=

______________________________________________________________________

     _______________________________________________

     Usatlas-hllhc-lartl2l3-l mailing list

Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
<mailto:Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>

     <mailto:Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>

https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l

--
---------------

Tim Andeen

Assistant Professor, Department of Physics

College of Natural Sciences

The University of Texas at Austin

Austin, TX 78712-1192

web: tandeen.web.cern.ch <http://tandeen.web.cern.ch>

office (TX): PMA 10.208

office (CERN): 304/1-024

ph (TX):  +1 512 475-9575

ph (CERN): +41 (0)22 76 758 14

email: tandeen AT utexas.edu <mailto:tandeen AT utexas.edu>
<mailto:tandeen AT utexas.edu>

---------------

--

______________________________________________________________________

John Parsons

Nevis Labs, Email: parsons AT nevis.columbia.edu <mailto:parsons AT nevis.columbia.edu>

  Columbia UniversityPhone: (914) 591-2820

P.O. Box 137Fax: (914) 591-8120

Irvington, NY 10533WWW: https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=Qc6SnqU6Ke4F9lJS7azkY9g_iCPu3hnSZpWn9SKRLRg&s=7pgN79h-hvnzfrN66TeuXY-xzWOgF2XY494XCtaX0LI&e=

______________________________________________________________________

_______________________________________________

Usatlas-hllhc-lartl2l3-l mailing list

Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <mailto:Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>

https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l


--
______________________________________________________________________

John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=aUYV8VK_m_eIuSQXGCzQAAF8CjfxfSlWl44oBi21DHk&s=7vrfEjifWyFsLkaA74SZX6CKczKCnq7g8lT2aaanBjI&e=


______________________________________________________________________




Archive powered by MHonArc 2.6.24.

Top of Page