usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Some BOE revisions needed for NSF FDR
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Some BOE revisions needed for NSF FDR
- Date: Mon, 5 Aug 2019 17:06:14 -0400
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] Some BOE revisions needed for NSF FDR
Date: Sat, 3 Aug 2019 13:24:25 -0400
From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
To: Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
Hello all,
Some BOE revisions will be needed for the NSF FDR:
-all mentions of "uncosted" labor need to be corrected to "scientific" labor
-if a BOE covers multiple institutions, ensure that all tables explicitly identify which institution is responsible for the costs
-most BOE tables will need to be updated: for many institutions rates needed to be adjusted to get the 1030s signed, so we will re-run all cost books.
The deadline for posting is August 16, expect the next two weeks to require the majority of your time to be dedicated to document preparation.
We will be preparing a full list of to-do items, and expect to send that out early next week.
Best,
Gustaaf
_______________________________________________
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l
- [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Some BOE revisions needed for NSF FDR, John Parsons, 08/05/2019
Archive powered by MHonArc 2.6.24.