  • From: "Ma, Hong" <hma AT bnl.gov>
  • To: "Parsons, John" <parsons AT nevis.columbia.edu>, Andy Haas <andy.haas AT nyu.edu>
  • Cc: John Hobbs <John.Hobbs AT stonybrook.edu>, "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] Items from the NSF meeting.
  • Date: Fri, 9 Aug 2019 14:54:23 +0000

 

                See the example in doc-db from Tile

 

   https://atlas-hllhc.docdb.bnl.gov/cgi-bin/private/ShowDocument?docid=906

 

                Hong.

 

From: John Parsons <parsons AT nevis.columbia.edu>
Date: Friday, August 9, 2019 at 10:43 AM
To: Andy Haas <andy.haas AT nyu.edu>
Cc: "Ma, Hong" <hma AT bnl.gov>, "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>, John Hobbs <John.Hobbs AT stonybrook.edu>
Subject: Re: [Usatlas-hllhc-lartl2l3-l] Items from the NSF meeting.

 

 

                As I explained also to John H. when I was at SBU,

you need to provide the files used to get the quotes

(eg. Gerber files, BOM).  They should all be uploaded to

a new docdb.  I will forward an email with more info.

 

                                John

 

On 8/9/19 9:36 AM, Andy Haas wrote:

Upload what to where?

On Fri, Aug 9, 2019 at 9:17 AM John Parsons <parsons AT nevis.columbia.edu> wrote:

 

 

Thanks, Hong.  Just arrived at CERN (6 hr delay!).

Will start to look into it.

 

Tim/Andy, for ICE you need to upload the various docs

in the spreadsheet (eg. Gerber, BOM) that they would

need to go for quotes.  Andy, John H. should have all

this.  I am afraid it is due today, so get right on it

and let me know when you have it.

 

                  John

 

On 8/8/19 3:39 PM, Ma, Hong wrote:

Hi John,

 

                   Just to let you know a few things discussed at the NSF

meeting today:

 

LAr needs to complete the ICE documents for each L3, due today.

 

                   Gustaaf sent a reminder today to L2/L3 mailing list.

 

                   Here is an example from Tile:

 

 

Need flowdown slides from L2.

 

                   Example from Tile is sent to L2 mailing list by Gustaaf

after the meeting.

 

                   This is for Sarah and Hal to pick some to be included

in their talks.

 

L2/3 talks:

 

                   Make sure they are split into two talks, technical and

management

 

                   And a few other changes listed in the todo list.

 

Deadline:

 

                   All materials (BOE, ICE etc) will need to be submitted

by Friday, Aug 16.

 

                   The website will be released to NSF and the committee,

and the files will be zipped and given to them too.

 

                   Hong.

 

 

--

______________________________________________________________________

 

John Parsons

Nevis Labs,             Email: parsons AT nevis.columbia.edu

    Columbia University   Phone: (914) 591-2820

P.O. Box 137            Fax: (914) 591-8120

 

______________________________________________________________________

_______________________________________________

Usatlas-hllhc-lartl2l3-l mailing list

 

--

______________________________________________________________________

 

John Parsons

Nevis Labs,                          Email: parsons AT nevis.columbia.edu

  Columbia University      Phone: (914) 591-2820

P.O. Box 137                       Fax: (914) 591-8120

 

______________________________________________________________________

 