Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] August status sheets

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: Tim Andeen <timothy.robert.andeen AT cern.ch>
  • To: John Parsons <parsons AT nevis.columbia.edu>
  • Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] August status sheets
  • Date: Fri, 23 Aug 2019 17:20:09 -0500

Hi John, 

Status sheets done. Some bullets for a monthly update are below. Best, Tim

ADC: submit chip to fabrication Aug 28. Simulations continuing, but promising results so far. 
Optics: lpGBT engineering chip design work mostly paused at request of CERN project. Should be able to finish by end of September. On the data/control links the "single channel" (adc emulator-> 1 lpGBT -> 1 VTRx) boards are designed and done. Early tests with lpGBT alone are good. in process now of ordering VTRx for complete tests. 

Best, Tim

On Tue, Aug 20, 2019 at 12:25 PM John Parsons <parsons AT nevis.columbia.edu> wrote:

As we are about to meet to discuss, among other
things, the July CPR, here is the request to fill
out the August status sheet.

                John

-------- Forwarded Message --------
Subject:        Re: [Usatlas-hllhc-l2l3ics-l] August status sheets
Date:   Tue, 20 Aug 2019 16:55:47 +0000
From:   Novakova, Penka N <penka AT bnl.gov>
To:     Freedman, Rhoumela <rfreedman AT bnl.gov>,
usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
<usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>



I’m sure you all are aware but a minor clarification, we are asking you
to not enter actual start/finish dates after August 31, 2019 in columns
M and N (not after July 31, 2019).

Thank you,

penka

*From:* Usatlas-hllhc-l2l3ics-l
<usatlas-hllhc-l2l3ics-l-bounces AT lists.bnl.gov> *On Behalf Of *Freedman,
Rhoumela
*Sent:* Tuesday, August 20, 2019 11:36 AM
*To:* usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
*Subject:* [Usatlas-hllhc-l2l3ics-l] August status sheets
*Importance:* High

Dear All,

*If you need help pleaseDO NOT replay to the mailing list*

The status sheets for the month of August are now available in google docs

   * 6.01 – Pixels -

https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1lg-5FT8BTl3rf-5F8c38D-2DLjpar9upSTWTy-2D-2D-5FSZxeWMkac_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=zWfA3_rvYCoy7F3PgxdrgMfuiK0VORFlw2eBWHDVKaU&s=SHX4kp4PpAS9764JCmzcIPxGPnTli1yV6179Xc2c3iY&e=

   * 6.02 – Strips -

https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1AhrbksKIvmaJz6gCAlFkT4nEYIBbuNTeRnNb-2DKd9LUs_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=zWfA3_rvYCoy7F3PgxdrgMfuiK0VORFlw2eBWHDVKaU&s=EKLj2_VTmCS51kakYxNBAz3bJYK9aETWvu0KAiSCbSg&e=
   * 6.03 – Global Mechanics -

https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1thvSdY2pMqMVwa-2DGbOXM-5F-5FUDPUINd8taPdsqOhyaQtw_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=zWfA3_rvYCoy7F3PgxdrgMfuiK0VORFlw2eBWHDVKaU&s=ZzGqadsgxPV3BuyMsyslgPiyGbTUv38ELaoPJWemqRk&e=

   * 6.04 – LAr -

https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_17XNToS4x2zGUOOa6-2Dp4XL-5Fjs8fqV4xeaQ14SBqrB8NI_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=zWfA3_rvYCoy7F3PgxdrgMfuiK0VORFlw2eBWHDVKaU&s=vDeKzDSe4c99u7sJ-ur7I2DtOsx_zmbjofvtfDAGNwE&e=

   * 6.05 – Tile –

https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1GDAKehlvi-5FsIuhV332058RCpueaBMZM7Tqhb3zFxOk8_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=zWfA3_rvYCoy7F3PgxdrgMfuiK0VORFlw2eBWHDVKaU&s=sCSc7NjBFXfR2vrUb06M0227V68INpYnE_zJFsNLX_g&e=

   * 6.06 – Muon -

https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1CDjxExTB-2D6RATnQQONZBjbue0eWz72pgBeHC0BNxHM8_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=zWfA3_rvYCoy7F3PgxdrgMfuiK0VORFlw2eBWHDVKaU&s=eUX3zaPjxVS0g5O6tE8wPqKfQAk2WXMTYPAFTNIw6Wc&e=

   * 6.07 – DAQ -

https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_10m-5F0Qxu-2Dl1rzWE0PoENGczxVTyC115E6UBgR7ke88oE_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=zWfA3_rvYCoy7F3PgxdrgMfuiK0VORFlw2eBWHDVKaU&s=UhHXzmgAWFomibDA8q06ff9cZNkgoA7jdmgKTL4dN3M&e=

   * 6.08 – Trigger -

https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1BCWYzO3iuhxwt4Egj6G-5FJM0V9msc89jpknBvErZ-5FIzQ_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=zWfA3_rvYCoy7F3PgxdrgMfuiK0VORFlw2eBWHDVKaU&s=6I7fkkE503RJP5fnvtALhrJ17vzDr6QOQqfH-AwYjuc&e=


Please remember to update the status online – DO NOT download the files.

The reports are at L2. The reports contain activities for July
2019-September 2020 in case some activities have started earlier. You
can filter for your CAM name in column D.

Please provide status in columns L, M, N, and O. Make sure that you
enter the actual start date for all started activities and finish date
for all activities that are 100% completed, this information is crucial
when we update the schedule in P6. If the activity is completed but you
do not remember the exact start and finish dates you can enter your best
estimate or copy the dates from the baseline start and finish dates (BL
Project Start/BL Project Finish). Do NOT enter dates after July 31, 2019
in actual start/finish dates (columns M and N) , this creates errors in
P6. Also do not write any notes in the spreadsheet, we may add a column
for comments in the future.

Please complete the July status update by */Monday, August 26/*.

We expect that the L2 managers and deputies will notify us (Penka,
Heidi, Carrie, Jenn) as soon as the status for their system is complete.

Let us know if you have any questions or comments/suggestions to make
the process smoother and more user-friendly.

Thank you!

Rhoumela Freedman, Administrator

U.S. ATLAS HL-LHC Upgrade Project

Brookhaven National Laboratory, Physics Dept.

Tel: (631) 344-3460

Fax: (631) 344-6179

rfreedman AT bnl.gov <mailto:rfreedman AT bnl.gov>

_______________________________________________
Usatlas-hllhc-lartl2l3-l mailing list
Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l


--
---------------
Tim Andeen
Assistant Professor, Department of Physics
College of Natural Sciences
The University of Texas at Austin
Austin, TX 78712-1192
web: tandeen.web.cern.ch
office (TX): PMA 10.208
office (CERN): 304/1-024
ph (TX):  +1 512 475-9575
ph (CERN): +41 (0)22 76 758 14
email: tandeen AT utexas.edu
---------------



Archive powered by MHonArc 2.6.24.

Top of Page