usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] ***CD-2/3 date -- Action Required***
- From: "Xu, Hao" <haoxu AT bnl.gov>
- To: "Parsons, John" <parsons AT nevis.columbia.edu>, "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] ***CD-2/3 date -- Action Required***
- Date: Thu, 10 Oct 2019 18:00:12 +0000
Hi John,
It works for me.
Regards,
Hao
Regards,
Hao
From: Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>
Sent: Thursday, October 10, 2019 1:20:17 PM
To: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] ***CD-2/3 date -- Action Required***
Sent: Thursday, October 10, 2019 1:20:17 PM
To: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] ***CD-2/3 date -- Action Required***
FYI. The DoE folks should let me know asap if the proposed
week is a problem.
John
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2deputymgmt-doe-l] ***CD-2/3 date -- Action
Required***
Date: Thu, 10 Oct 2019 17:11:18 +0000
From: Kotcher, Jonathan <kotcher AT bnl.gov>
To: usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov
<usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov>
All –
DOE has requested that we reserve time on the OPA calendar for the
CD-2/3 review next year. It will not be binding, but is something that
should be realistic and that we do all we can to hold to.
We in the PO have folded in our view of overall project readiness,
significant ATLAS meetings that present conflicts, availability of
agency personnel, and several other issues. *We’ve settled on the week
of December 7, 2020 as the most desirable week.* Note that there are
not many candidate dates, so we should make every effort to accommodate
this.
**
*Please run this by the people in your subprojects and let us know of
any serious conflicts*, *getting back to me by 1pm eastern tomorrow*,
*Friday, 10/11.* We have been asked to respond tomorrow.
My apologies for the short time scale, but it could not be helped. It’s
in our interest to proactively set a date for this and, among other
things, to start focusing the baseline discussions at all levels –
within the US project, US ATLAS more broadly, the agencies, and with
International ATLAS and CERN.
Many thanks -- cheers -- Jon
-
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] ***CD-2/3 date -- Action Required***,
John Parsons, 10/10/2019
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] ***CD-2/3 date -- Action Required***, Xu, Hao, 10/10/2019
Archive powered by MHonArc 2.6.24.