A reminder to everyone (except Hao, who has completed it) that this is overdue. Please do it today!
Thanks,
John
On 2/22/20 12:59 PM, John Parsons wrote:
Hi all,
It is time for the Feb. status sheet (see below) as well as to send me the technical progress bullets. The request came a bit late this month, so please take care of by Monday COB, and let me know when you are done.
Thanks,
John
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] February 2020 Status Sheets
Date: Sat, 22 Feb 2020 17:40:59 +0000
From: Freedman, Rhoumela <rfreedman AT bnl.gov>
To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
Dear All,
*If you need help pleaseDO NOT reply to the mailing list*
**** The Pre-Status Reports for February 2020 have been uploaded in *DocDB 976*. These are the Gantt Charts for each subsystem. Please make sure to look over the chart while doing your Status Updates. ****
The status sheets for the month of November are now available in google docs
* 6.01 - Pixels - *** UPDATED SHEET TO BE DIRECTLY EMAILED TO TEAM ***
* 6.02 - Strips -
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/13ymCzMQFPXpSTy1R_bSqSnqmvney49Evtz6HpF2YwKE/edit?usp=sharing__;!!P4SdNyxKAPE!Vaya9z-RBLP0cN2WKVuth-UbcCS-rxmUT6-552Nl4wS_JprmOk3D2WcqdFG7EazVv5BTDBZ1qXTIXMjp8jZv$
* 6.03 - Global Mechanics
-https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1hP8dA_CE5qeNQ0pjvKFY1ypyODqtm34RWutZZM1dr1A/edit?usp=sharing__;!!P4SdNyxKAPE!Vaya9z-RBLP0cN2WKVuth-UbcCS-rxmUT6-552Nl4wS_JprmOk3D2WcqdFG7EazVv5BTDBZ1qXTIXAzljLOh$
* 6.04 - LAr -
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1nvkqTGbXrg2VyOE-OLsG6OuyPQDh8unt4SGiwrO3JTM/edit?usp=sharing__;!!P4SdNyxKAPE!Vaya9z-RBLP0cN2WKVuth-UbcCS-rxmUT6-552Nl4wS_JprmOk3D2WcqdFG7EazVv5BTDBZ1qXTIXCguUOKC$
* 6.05 - Tile -
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1hcxCqOHSsdWa1fSYpjBd_nZQAcPRp137DAYv1jpcsoo/edit?usp=sharing__;!!P4SdNyxKAPE!Vaya9z-RBLP0cN2WKVuth-UbcCS-rxmUT6-552Nl4wS_JprmOk3D2WcqdFG7EazVv5BTDBZ1qXTIXP9Rm5yG$
* 6.06 - Muon -
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/15Rx6fxpBSLbz2gx1LF2k7J7nKyDSnP1CRub9cI94q_8/edit?usp=sharing__;!!P4SdNyxKAPE!Vaya9z-RBLP0cN2WKVuth-UbcCS-rxmUT6-552Nl4wS_JprmOk3D2WcqdFG7EazVv5BTDBZ1qXTIXPTkZx4r$
* 6.07 - DAQ -
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1_Tf-Vbm5RxBoIDsjwKt_GRZvnMRe6yR9Luy6VSJ6eXw/edit?usp=sharing__;!!P4SdNyxKAPE!Vaya9z-RBLP0cN2WKVuth-UbcCS-rxmUT6-552Nl4wS_JprmOk3D2WcqdFG7EazVv5BTDBZ1qXTIXC3fxeqW$
* 6.08 - Trigger -
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1cx-SL2d9_wIccCJAZbSSivazKSf-bKXuNA93PduqYRU/edit?usp=sharing__;!!P4SdNyxKAPE!Vaya9z-RBLP0cN2WKVuth-UbcCS-rxmUT6-552Nl4wS_JprmOk3D2WcqdFG7EazVv5BTDBZ1qXTIXFtp5hzg$
Please remember to update the status online – DO NOT download the files.
The reports are at L2. The reports contain activities for October 2019-September 2020 in case some activities have started earlier. You can filter for your CAM name in column D.
**** PLEASE NOTE THE FOLLOWING INSTRUCTIONS IN FILLING OUT YOUR STATUS SHEETS: ****
1. Please provide status in columns L, N, and O.
2. Make sure that you enter the actual start date for all started
activities and finish date for all activities that are 100%
completed. All *_NEW_* actual start and finish dates *MUST BE*
within current reporting period.
3. Do *NOT *change the actual start/finish dates in they are already in
the spreadsheet – EVMS does not allow changing the past. If the
actual start date was entered incorrectly in the previous month just
leave it as it is.
4. Do *NOT* enter dates after January 31, 2020 in actual start/finish
dates (columns N and O) , this creates errors in P6.
5. Do *NOT* decrease percent complete in column L.
6. Do *NOT* write any notes in the spreadsheet, if you want to add a
comment use column AC.
Please complete the February status update by Wednesday, February 26.
We expect that the L2 managers and deputies will notify us (Penka, Carrie, Jenn, Rhoumela) as soon as the status for their system is complete.
Let us know if you have any questions or comments/suggestions to make the process smoother and more user-friendly.
Thank you!
Rhoumela
Rhoumela Freedman, Administrator
U.S. ATLAS HL-LHC Upgrade Project
Brookhaven National Laboratory, Physics Dept.
Tel: (631) 344-3460
Fax: (631) 344-6179
rfreedman AT bnl.gov <mailto:rfreedman AT bnl.gov>
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!Vaya9z-RBLP0cN2WKVuth-UbcCS-rxmUT6-552Nl4wS_JprmOk3D2WcqdFG7EazVv5BTDBZ1qXTIXMOTXd9U$
______________________________________________________________________
-
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] February 2020 Status Sheets,
John Parsons, 02/22/2020
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] February 2020 Status Sheets, John Parsons, 02/25/2020
Archive powered by MHonArc 2.6.24.