Hi all,

We will meet on Friday this week at the usual 1 pm NY time. Indico is at https://indico.bnl.gov/event/10007/. In addition to the usual roundtable, we will discuss the upcoming NSF COVID BCP (see below).
Regards,
John

-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] NSF Covid-19 change
Date: Wed, 4 Nov 2020 20:46:31 +0000
From: Novakova, Penka N <penka AT bnl.gov>
To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>



This message is for NSF CAMs only

As discussed we will start working on the NSF COVID-19 change request. For this purpose Jenn has generated excel spreadsheets and Rhoumela has posted them in google docs

* 6.04 - LAr -

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1iOwoZVNiP8UmMsGnLIaZNlgETinIqIibZ9nV8uUuU9o/edit?usp=sharing__;!!P4SdNyxKAPE!XyAyLmYtMXgbfSiuQ8UYb5qR8bpCIfCPvvqBZX1XdSnFc_n9SEb1Xb1Mk1RXoC-tt6ejUr5cdsmbexDR7UuC$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1iOwoZVNiP8UmMsGnLIaZNlgETinIqIibZ9nV8uUuU9o/edit?usp=sharing__;!!P4SdNyxKAPE!XyAyLmYtMXgbfSiuQ8UYb5qR8bpCIfCPvvqBZX1XdSnFc_n9SEb1Xb1Mk1RXoC-tt6ejUr5cdsmbexDR7UuC$
>
* 6.05 – Tile -

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1b4Kn4N96dsikSHZHtVuhiqTUwMsuFYRjE21YoJrDMMk/edit?usp=sharing__;!!P4SdNyxKAPE!XyAyLmYtMXgbfSiuQ8UYb5qR8bpCIfCPvvqBZX1XdSnFc_n9SEb1Xb1Mk1RXoC-tt6ejUr5cdsmbe6PRA43a$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1b4Kn4N96dsikSHZHtVuhiqTUwMsuFYRjE21YoJrDMMk/edit?usp=sharing__;!!P4SdNyxKAPE!XyAyLmYtMXgbfSiuQ8UYb5qR8bpCIfCPvvqBZX1XdSnFc_n9SEb1Xb1Mk1RXoC-tt6ejUr5cdsmbe6PRA43a$
>

* 6.06 – Muon -

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/19dJjzSvFYpt2DZiBXlX8LVRNeRPGyb0Tjqx76-_7wPU/edit?usp=sharing__;!!P4SdNyxKAPE!XyAyLmYtMXgbfSiuQ8UYb5qR8bpCIfCPvvqBZX1XdSnFc_n9SEb1Xb1Mk1RXoC-tt6ejUr5cdsmbe5ioUDqv$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/19dJjzSvFYpt2DZiBXlX8LVRNeRPGyb0Tjqx76-_7wPU/edit?usp=sharing__;!!P4SdNyxKAPE!XyAyLmYtMXgbfSiuQ8UYb5qR8bpCIfCPvvqBZX1XdSnFc_n9SEb1Xb1Mk1RXoC-tt6ejUr5cdsmbe5ioUDqv$
>
* 6.08 – Trigger -

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/10WfXjJeTreiqyJ6tyEuMOP6nfUlPJP6vTEoYBQlAp00/edit?usp=sharing__;!!P4SdNyxKAPE!XyAyLmYtMXgbfSiuQ8UYb5qR8bpCIfCPvvqBZX1XdSnFc_n9SEb1Xb1Mk1RXoC-tt6ejUr5cdsmbexagd-G2$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/10WfXjJeTreiqyJ6tyEuMOP6nfUlPJP6vTEoYBQlAp00/edit?usp=sharing__;!!P4SdNyxKAPE!XyAyLmYtMXgbfSiuQ8UYb5qR8bpCIfCPvvqBZX1XdSnFc_n9SEb1Xb1Mk1RXoC-tt6ejUr5cdsmbexagd-G2$
>

Here are the instructions for providing feedback to the project controls team.

The sheets are based on the October status working schedule. They are similar to the status sheets but have some differences.

In the sheets there are 2 tabs

1. In-progress activities
2. Not started activities that have baseline dates between April 1,
2020 and March 31, 2021

For activities **in-progress**

As described in the Gustaaf’s presentation (attached) these activities will be split – the first activity will have baseline start as in the current schedule and completion date of October 31, 2020. The second activity will have the same description with **(2)** at the end. Therefore we are not asking you to add new activity but rather provide information for this new activity in columns Q, R, S, T.

Planned units of the first activity will be calculated based on **Planned Units**(column N) minus **Remaining Units**(column O).

For **Not started** activities.

If you know how their durations/start/finish dates have changed please provide this is columns P, Q, R, S. If you don’t have information leave them as they are. Only change effort and/or duration if task will be done in near future (< 6 months)

Keep in mind that activities with baseline start date before November 1, 2020 should be moved after Nov 1 otherwise we will get schedule variance once we start statussing the updated schedules.

If you know that travel will not happen add comment in column U so we know that the activity should be deleted.

We would like to get feedback as soon as possible but not later than Wednesday, Nov 11.

If you have any questions please let us know.

Best,

Penka, Carrie, Jenn, Rhoumela

Penka Novakova

U.S. ATLAS HL-LHC Project Office

Bldg. 510

Brookhaven National Lab

Upton, NY 11973

Tel. 631-344-2502

Attachment: 2020-10-16-COVID-BCP-NSF.pdf
Description: Adobe PDF document

_______________________________________________
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l



Archive powered by MHonArc 2.6.24.

Top of Page