usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
Re: [Usatlas-hllhc-lartl2l3-l] [Usatlas-hllhc-l2deputymgmt-doe-l] Scrubbing meetings for DOE review
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "Meyer, Christopher John" <cjmey AT iu.edu>, "usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov>
- Cc: "George Redlinger \(george.redlinger AT cern.ch\)" <george.redlinger AT cern.ch>, "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>, "usatlas-hllhc-management-l AT lists.bnl.gov" <usatlas-hllhc-management-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] [Usatlas-hllhc-l2deputymgmt-doe-l] Scrubbing meetings for DOE review
- Date: Fri, 8 Oct 2021 14:05:29 -0400
I attach my notes from today's discussion.
John
On 10/7/21 11:23 AM, John Parsons wrote:
Hi all,
A reminder that the LAr DoE RR scrubbing meeting will take place tomorrow starting at 12:30 pm EDT.
Regards,
John
On 9/24/21 4:30 PM, John Parsons wrote:
Hi Chris,
Here is the agenda page and Zoom link for LAr:
https://indico.bnl.gov/event/13300/.
John
On 9/24/21 4:10 PM, Meyer, Christopher John wrote:
Dear DOE L2s,
After talking with the PO, it would be best if you can create the agenda for your respective risk scrubbing events so that you have ownership.
An example has already been created for Pixels:
https://indico.bnl.gov/event/13276/ <https://indico.bnl.gov/event/13276/>
You are welcome to clone this, including the Zoom link, and simply change the presentations to match your own L3s.
Thanks, and have a nice weekend!
Chris, Chris & George
*From: *Usatlas-hllhc-l2deputymgmt-doe-l <usatlas-hllhc-l2deputymgmt-doe-l-bounces AT lists.bnl.gov> on behalf of Meyer, Christopher John <cjmey AT iu.edu>
*Date: *Tuesday, September 21, 2021 at 2:22 PM
*To: *usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov>
*Cc: *George Redlinger (george.redlinger AT cern.ch) <george.redlinger AT cern.ch>, usatlas-hllhc-management-l AT lists.bnl.gov <usatlas-hllhc-management-l AT lists.bnl.gov>
*Subject: *Re: [Usatlas-hllhc-l2deputymgmt-doe-l] Scrubbing meetings for DOE review
Dear DOE L2s/DL2s,
Thanks a lot for your help scheduling the scrubbing meetings for our upcoming DOE reviews. The final schedule is:
- Pixel: Tues, Sep 28 from 2–4 PM EDT
- Strips: Thurs, Sep 30 from 3–5 PM EDT
- DAQ: Fri, Oct 1 from 4–6 PM EDT
- GM: Mon, Oct 4 from 3–5 PM EDT
- LAr: Friday, Oct 8 from 12:30–2:30 PM EDT
We would propose following the same approach as in the past, namely that we have a presentation by each L3, with one slide per risk (using the template in the “detailed view” tab in the risk register xlsx file). There could be a short overview by the L2, if this would be helpful to understand the overall context. The main things we want to cover are:
- Is everything up to date? (Expiration, cost/schedule impacts, comments, task affected)
- Are there new risks?
- Any questions from the PMO on the existing risk documentation (consistency across risks, comments are sufficiently explanatory)
- COVID vendor risks: expect a more detailed email on this topic soon
* Special to Strips: is the Standing Army analysis up to date? (Maybe this has to be covered by the L2)
The most up-to-date risk register can be found here:
https://atlas-hllhc.docdb.bnl.gov/0001/000196/063/Risk-Register_v61.xlsx <https://atlas-hllhc.docdb.bnl.gov/0001/000196/063/Risk-Register_v61.xlsx>
We are arranging for the usual agendas with connection details and will follow-up when they’re available. In the meantime, please reach out with any questions you may have.
Cheers,
Chris, Chris & George
*From: *Meyer, Christopher John <cjmey AT iu.edu>
*Date: *Tuesday, September 7, 2021 at 3:30 PM
*To: *usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov>, usatlas-hllhc-management-l AT lists.bnl.gov <usatlas-hllhc-management-l AT lists.bnl.gov>
*Cc: *George Redlinger (george.redlinger AT cern.ch) <george.redlinger AT cern.ch>, Bee, Christopher (Contact) <christopher.bee AT stonybrook.edu>
*Subject: *Scrubbing meetings for DOE review
Dear DOE L2s/DL2s,
In preparation for the upcoming DOE reviews, we'd like to start scheduling scrubbing meetings to update the risk simulation. As a first attempt, would you please respond to Chris, George and myself on your general availability the weeks of Sep 27 and Oct 4? This avoids the upcoming TDAQ week (Sep 20) and ATLAS week (Oct 11).
Thanks,
Chris M, Chris B & George
_______________________________________________
Usatlas-hllhc-l2deputymgmt-doe-l mailing list
Usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-doe-l
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!VbZnZ_yBgwc5d0kdaKCBxCn-K-4Mn7abKtOnx3J1hoQikHJiVgSdBjo3jx5XtArSIsKQkbU8Bfy1u7PO0c8u$
______________________________________________________________________
Attachment:
LArDoERiskScrubbing20211008.docx
Description: application/vnd.openxmlformats-officedocument.wordprocessingml.document
-
Re: [Usatlas-hllhc-lartl2l3-l] [Usatlas-hllhc-l2deputymgmt-doe-l] Scrubbing meetings for DOE review,
John Parsons, 10/07/2021
- Re: [Usatlas-hllhc-lartl2l3-l] [Usatlas-hllhc-l2deputymgmt-doe-l] Scrubbing meetings for DOE review, John Parsons, 10/08/2021
Archive powered by MHonArc 2.6.24.