Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-l] FW: Site for HL-LHC US ATLAS Upgrade Project Director's Review, December 13-15, 2021

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-l] FW: Site for HL-LHC US ATLAS Upgrade Project Director's Review, December 13-15, 2021
  • Date: Mon, 6 Dec 2021 22:36:00 -0500


FYI

-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2deputymgmt-l] FW: Site for HL-LHC US ATLAS Upgrade Project Director's Review, December 13-15, 2021
Date: Tue, 7 Dec 2021 03:31:40 +0000
From: Kotcher, Jonathan <kotcher AT bnl.gov>
To: usatlas-hllhc-l2deputymgmt-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-l AT lists.bnl.gov>



All –

Below, the site and a bit of navigation assistance for the DR committee.  Please pass along within your systems.

Best –

Jon, for the PO

*From: *Denisov, Dmitri <denisovd AT bnl.gov>
*Date: *Monday, December 6, 2021 at 6:10 PM
*To: *Yoshida, Rikutaro (ryoshida AT anl.gov) <ryoshida AT anl.gov>, Ruben H Carcagno <ruben AT fnal.gov>, Gutta, Rajendra Rao <rgutta AT bnl.gov>, David A. Leeb <dleeb AT fnal.gov>, Vaia Papadimitriou <vaia AT fnal.gov>, Marco Verzocchi (mverzocc AT fnal.gov) <mverzocc AT fnal.gov>, Nicola Bacchetta <nicola.bacchetta AT cern.ch>, Karl Matthew Ecklund <Karl.Ecklund AT rice.edu>, lipton AT fnal.gov <lipton AT fnal.gov>, ulrich_heintz AT brown.edu (ulrich_heintz AT brown.edu) <ulrich_heintz AT brown.edu>, Mar Capeans Garrido <Mar.Capeans AT cern.ch>, Fouts, Ken <kfouts AT slac.stanford.edu>, Sondheim, Walter E <sondheim AT lanl.gov>, Carini, Gabriella <carini AT bnl.gov>, Paul M Rubinov (rubinov AT fnal.gov) <rubinov AT fnal.gov>, Ted Liu (thliu AT fnal.gov) <thliu AT fnal.gov>, Roger W Rusack (rusack AT umn.edu) <rusack AT umn.edu>
*Cc: *Yemi Tomori <atomori AT fnal.gov>, Davis, Drew <jdavis AT bnl.gov>, Kotcher, Jonathan <kotcher AT bnl.gov>
*Subject: *Site for HL-LHC US ATLAS Upgrade Project Director's Review, December 13-15, 2021

Dear Rik, Ruben, Raj, David, Vaia, Marco, Nicola, Karl, Ron, Uli, Mar, Kem, Walter, Gabriella, Paul, Ted and Roger!

Thank you again for serving on this review committee and evaluating HL-LHC US ATLAS project status and plans. We have new member of the committee, Karl Ecklund, who stepped in to replace unavailable committee member. Thank you Karl!

The link and access information for the review site are

https://po.usatlas.bnl.gov/HL-LHC/reviews/IPR&CD-3b-DR-Dec13-15-2021/ <https://po.usatlas.bnl.gov/HL-LHC/reviews/IPR&CD-3b-DR-Dec13-15-2021/>

Username = review

Password = p2-hlc (to be used for all prompts)

A few notes

* All material updated for this status review may be found under the
headings “Review Committee Materials” and “Project Documentation”.
The sole exception is the “Cost Estimating Plan” under the
“Management Documentation” heading, which has also been updated.  In
keeping with the nature of such a status review, all other
information under “Management Documentation” and “Additional
Material” – PMP, PEP, TDRs, etc. -- may be of interest to you, but
should be treated as essentially archival.
* The presentations can be found under the first major heading “Review
Committee Materials” at the “Indico Presentations” link.  You might
want to consider starting with these.
* The breakout talks are ~ 30’ in duration. These talks are under one
Indico heading on Monday afternoon for each subsystem. They are
intended to provide the basis for the breakouts on Monday afternoon
and all-day Tuesday.
* The material under the “Project Documentation” heading contains the
suite of updated project material for this review:  cost books, risk
register, BoEs, KPPs, etc.
* Several talks remain to be uploaded but most everything should be up
by tonight (December 6) or early tomorrow morning – any changes that
might be made after that time will be incremental.

Zoom coordinates for the plenary, executive and parallel sessions are on the top of the review Indico page.

If there are questions of any kind, including issues with accessing the information, please don’t hesitate to get in touch with myself or Jon Kotcher (CCed).

Stay safe, Dmitri.
_______________________________________________
Usatlas-hllhc-l2deputymgmt-l mailing list
Usatlas-hllhc-l2deputymgmt-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-l


  • [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-l] FW: Site for HL-LHC US ATLAS Upgrade Project Director's Review, December 13-15, 2021, John Parsons, 12/06/2021

Archive powered by MHonArc 2.6.24.

Top of Page