Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] Scheduling CD-2/3 and Director's Review

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] Scheduling CD-2/3 and Director's Review
  • Date: Thu, 16 Dec 2021 10:14:59 -0500


Hi all,

It has proven very difficult to schedule the DoE CD-2/3 review, so Jon has prepared a new doodle poll with weeks from end of August through end of November. I need Hong and Hao to let me know asap which weeks are NOT possible for them. After collecting those and my own availability, I will fill out the poll for the LAr group. We are asked to be as flexible as possible, given the importance of getting this baseline review passed as soon as possible.
Thanks,
John

-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2deputymgmt-doe-l] Scheduling CD-2/3 and Director's Review
Date: Thu, 16 Dec 2021 13:28:48 +0000
From: Kotcher, Jonathan <kotcher AT bnl.gov>
To: usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov>



All –

Below, please find the link to a DOODLE poll for the weeks of August 29 through November 28, 2022, inclusive, for scheduling the CD-2/3 review.  Please fill it out with your teams as soon as possible – as before, one entry per system. As I mentioned yesterday, the OPA calendar is filling up quite rapidly lately -- they’re already booked through next summer.  We want to identify a slot as soon as possible.

Also, a reminder that we’ve all agreed put aside the week of June 27, 2022 for a Director’s Review in preparation for a fall CD-2/3.  We’ll nail down specific days in the near future.  Please make sure you and your teams mark your calendars.

Thanks very much – any questions, just contact us –

Cheers – Jon, for the PO

https://urldefense.com/v3/__https://doodle.com/poll/z7sfadb7qzsrvgcq?utm_source=poll&utm_medium=link__;!!P4SdNyxKAPE!TILZNg0ZmnpDpEgPiJk_OfmPhtA7pbqpFA-mYSNicxK_ECr1nTS8T8RjIebABPmEJ8DtGJ6d91rrsld2NlTS$ <https://urldefense.com/v3/__https://doodle.com/poll/z7sfadb7qzsrvgcq?utm_source=poll&utm_medium=link__;!!P4SdNyxKAPE!TILZNg0ZmnpDpEgPiJk_OfmPhtA7pbqpFA-mYSNicxK_ECr1nTS8T8RjIebABPmEJ8DtGJ6d91rrsld2NlTS$ >
_______________________________________________
Usatlas-hllhc-l2deputymgmt-doe-l mailing list
Usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-doe-l


  • [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] Scheduling CD-2/3 and Director's Review, John Parsons, 12/16/2021

Archive powered by MHonArc 2.6.24.

Top of Page