Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] December 2021 Status Sheets

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] December 2021 Status Sheets
  • Date: Wed, 22 Dec 2021 14:48:02 -0500


Hi all,

It is status and technical bullets time again. Thanks to Tim who already completed them! Everyone else, please take care of both by Tues. Dec. 28 (the deadlines are later this month due to the holidays, plus the PO was focused on the DoE DR).
Thanks,
John

-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] December 2021 Status Sheets
Date: Mon, 20 Dec 2021 17:46:54 +0000
From: Freedman, Rhoumela <rfreedman AT bnl.gov>
To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>



Dear All,

*If you need help pleaseDO NOTreply to the mailing list*

**** The*/Pre-Status Reports/*//*/for December 2021/*have been uploaded in*DocDB 976*. These are the Gantt Charts for each subsystem.  Please make sure to look over the chart while doing your Status Updates. ****

The UPDATED status sheets for the month of December are now available in google docs:

* *6.01 – Pixels -

*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1GiybkTLvZ0Y9vd8Os3mqqIof7J72OEZWle7MycM-mps/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJPO66Qt2$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1GiybkTLvZ0Y9vd8Os3mqqIof7J72OEZWle7MycM-mps/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJPO66Qt2$
>
* *6.02 – Strips * -

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1WjSGByXwGhzAsKTSyoLWEWKel_bXOpMnIOXmPKwsBM8/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJA8LTnBO$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1WjSGByXwGhzAsKTSyoLWEWKel_bXOpMnIOXmPKwsBM8/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJA8LTnBO$
>

* *6.03 – Global Mechanics -

*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/141ABj_9h6Ig0ut4zyTPlSABX04yMfOIpcgEhuGDyjIw/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJGmsqH1Z$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/141ABj_9h6Ig0ut4zyTPlSABX04yMfOIpcgEhuGDyjIw/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJGmsqH1Z$
>
* *6.04 – LAr -*

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1abINlNkALPYKyQiryoiiS30u_Tpxnh-EAZmWIRJCXqk/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJDWQOXl1$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1abINlNkALPYKyQiryoiiS30u_Tpxnh-EAZmWIRJCXqk/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJDWQOXl1$
>

* *6.05 – Tiles -

*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/118Z3f4FTqot4VU5uy3utj37reGuWh6NfmlMb7SPCgYA/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJCVfzJD8$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/118Z3f4FTqot4VU5uy3utj37reGuWh6NfmlMb7SPCgYA/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJCVfzJD8$
>
* *6.06 – Muons -

*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/16DTfdPgS0465o5UbaXvySWtyq0Y1_w93OTYOz0zsSsc/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJMOd8GFd$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/16DTfdPgS0465o5UbaXvySWtyq0Y1_w93OTYOz0zsSsc/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJMOd8GFd$
>
* *6.07 – DAQ -

*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1dd5DkgCZWpAOCyRalZqJdaFeE_VNstZ60MdvI0Nz_4U/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJNAZ1znO$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1dd5DkgCZWpAOCyRalZqJdaFeE_VNstZ60MdvI0Nz_4U/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJNAZ1znO$
>
* *6.08 – Trigger - *

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1XruxvuhvFd4hOfKcIXRB5b3LMOblHzGuucm5oWL6ZlI/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJCZChg0E$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1XruxvuhvFd4hOfKcIXRB5b3LMOblHzGuucm5oWL6ZlI/edit?usp=sharing__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJCZChg0E$
>


Please remember to update the status online –DO NOT downloadthe files.

The reports are at L2. The reports contain activities for December 2021-June 2022. You can filter for your CAM name in column D.

**** PLEASE NOTE THE FOLLOWING INSTRUCTIONS IN FILLING OUT YOUR STATUS SHEETS: ****

1. Please provide status in columns L, M, N, O, and S. Make sure that
for all activities in progress you provide **Expected Finish**
(column O). This is important for us to re-calculate the float and
the critical path.
2. The remaining units are calculated based on the original duration of
the activity and percent complete. We have added *column S*in which
we are asking you to update the **Units to Complete** based on your
experience and expectations. This is only in case you expect to
spend more or less labor for the specific activity or the cost for
material/travel is different than originally estimated. Column T
show Total Cost per resource  from P6. Columns U (Remaining Cost
based on the remaining units from P6), V (Updated Remaining Cost,
also called ETC or Estimate-to-Complete), W (EAC or Estimate at
Complete, calculated based on updated units) and X (Delta EAC minus
baseline cost) are formula fields that provide calculations on how
the cost changes when the Remaining Units are adjusted.
3. Make sure that you enter the actual start date for all started
activities and finish date for all activities that are 100%
completed. All*_NEW_*actual start and finish dates*MUST BE*within
current reporting period.
4. Do*NOT*change the actual start/finish dates if they are already in
the spreadsheet – EVMS does not allow changing the past. If the
actual start date was entered incorrectly in the previous month just
leave it as it is.
5. Do*NOT*enter dates after December 31, 2021  in actual start/finish
dates (columns M and N) , this creates errors in P6.
6. Do*NOT*decrease percent complete in column L.
7. Do*NOT*write any notes in the spreadsheet, if you want to add a
comment use column Y.
8. Do*NOT*change the formatting of the cell once you edit it.  The
spreadsheet will automatically highlight the change in yellow.
*_Additional Note: _*

If progress was made on future activities that are not in the status sheet you can contact your project controls specialist and ask for her help with statussing the activities directly in P6.

Please complete the October status update by*Monday*,*January 3*.

We expect that the L2 managers and deputies will notify us (Penka,  Carrie, Jenn, Rhoumela) as soon as the status for their system is complete.

Rhoumela Freedman, Administrator
U.S. ATLAS HL-LHC Upgrade Project

Brookhaven National Laboratory, Physics Dept.

Tel: (631) 344-3460

Fax: (631) 344-6179

rfreedman AT bnl.gov <mailto:rfreedman AT bnl.gov>

<https://www.bnl.gov/>
Twitter <https://urldefense.com/v3/__https://twitter.com/BrookhavenLab__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJINuZmdF$ > | Facebook <https://urldefense.com/v3/__https://www.facebook.com/brookhavenlab__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJNrmBHW0$ > | Instagram <https://urldefense.com/v3/__https://www.instagram.com/brookhavenlab/__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJCcLn95B$ > | LinkedIn <https://urldefense.com/v3/__https://www.linkedin.com/company/brookhavenlab/__;!!P4SdNyxKAPE!SNPiL3ZsgJcuR-xEcv7nzxyUimNkUn4CcqsauDtKoQlSq5AC1mLSpGAhwJJzxsbq_xpqaBtCUYSpJMMdeB0M$ >
_______________________________________________
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l


  • [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] December 2021 Status Sheets, John Parsons, 12/22/2021

Archive powered by MHonArc 2.6.24.

Top of Page