  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] October 2022 Status Sheets
  • Date: Thu, 20 Oct 2022 14:59:53 -0400


It is monthly status and technical bullets time again. Please complete both by Tues. next week at the latest.

John

P.S. A reminder that we will not meet Friday this week, since a number of us are busy with the ongoing DOE CD-2/3 review.


-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] October 2022 Status Sheets
Date: Thu, 20 Oct 2022 15:25:44 +0000
From: Smith, Rosemarie <rsmith2 AT bnl.gov>
To: Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>



Dear All,

*If you need help, please DO NOT reply to the mailing list*

The Gantt Charts for each subsystem has been uploaded in *DocDB 976*. Please make sure to look over them while statusing the activities.

Status sheets for October are now available in google docs:

* *6.01 Pixels: *

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1OcFRA2Thcmil_gLF2XJtNk4rMuqPrnDFpwkqI7mTYRk/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PN6MmVXRw$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1OcFRA2Thcmil_gLF2XJtNk4rMuqPrnDFpwkqI7mTYRk/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PN6MmVXRw$
>
* *6.02 Strips:

*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/14Pz_ZK_M1Y230-q1idNFuO1IlKvyJsuSU1PyLzKZ3Po/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PNpUlHZNg$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/14Pz_ZK_M1Y230-q1idNFuO1IlKvyJsuSU1PyLzKZ3Po/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PNpUlHZNg$
>

* *6.03 Global Mechanics: *

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1z71bHeygV12BNvD-7tvRj3Ras2XjG9cfWNeLrdx7v3U/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95POhlxQU3g$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1z71bHeygV12BNvD-7tvRj3Ras2XjG9cfWNeLrdx7v3U/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95POhlxQU3g$
>
* *6.04 Lar:

*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1o6naGVrv35_leApxlaRSwkNtHEebrVM1emgZb8wL_u4/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PNa53bGww$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1o6naGVrv35_leApxlaRSwkNtHEebrVM1emgZb8wL_u4/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PNa53bGww$
>

* *6.05 Tiles:

*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1Z7VHXu_0V7z0FYckt45SDh2dV4p_utNWS3XCi1WBb5U/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PM47tmlTg$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1Z7VHXu_0V7z0FYckt45SDh2dV4p_utNWS3XCi1WBb5U/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PM47tmlTg$
>**
* *6.06 Muons:*

https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/14eNzZeSE5jF7mDj2J00sWMnUbwu9e3kL38nuq5mY_RE/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PPhmsrCxg$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/14eNzZeSE5jF7mDj2J00sWMnUbwu9e3kL38nuq5mY_RE/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PPhmsrCxg$
>

* *6.07 DAQ:

*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1h25EKUNe_Jt08WxL5OJMg6oDFIigCwEjlmG96XqbarI/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PPA3WCwIg$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1h25EKUNe_Jt08WxL5OJMg6oDFIigCwEjlmG96XqbarI/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PPA3WCwIg$
>

* *6.08 Trigger:

*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1pZpeOwXYpWOStsi0ZOaNqDY-mr_hI4sZoXvlhxPnvRg/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PO_cNwe1w$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1pZpeOwXYpWOStsi0ZOaNqDY-mr_hI4sZoXvlhxPnvRg/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PO_cNwe1w$
>**
* *6.11 Installation & Integration:

*https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1mlFCuS6pRPhoUPq8N9pHdff9fvnGx5OnPhe5DMWITg0/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PPehajJ6A$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1mlFCuS6pRPhoUPq8N9pHdff9fvnGx5OnPhe5DMWITg0/edit?usp=sharing__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PPehajJ6A$
>**

Please remember to update the status online – DO NOT download the files.

The reports contain activities for October 2022 ~ March 2023. You can filter for your CAM name in column D.

We included a status sheet for 6.11 I&I for the first time since the work is supposed to start in October/November 2022.

**** PLEASE NOTE THE FOLLOWING INSTRUCTIONS IN FILLING OUT YOUR STATUS SHEETS: ****

1. Please provide the status in columns L, M, N, O, and S. Make sure
you provide the **Expected Finish** date (column O) for all
*activities in progress*. This is important for us to re-calculate
EAC, the float, and the critical path.
2. The remaining units are calculated based on the original duration of
the activity and the percent complete. Please provide **Units to
Complete* in column S* for activities in progress. It is if you
expect to use more or less labor for a specific task to be completed
or the cost for material/travel is different than originally
planned. Column T shows Total Cost per resource from P6. Columns U
(Remaining Cost based on the remaining units from P6), V (Updated
Remaining Cost, also called ETC or Estimate-to-Complete), W (EAC or
Estimate at Complete, calculated based on updated units) and X
(Delta EAC minus baseline cost) are formula fields that provide
calculations on how the cost changes when the Remaining Units are
adjusted.
3. Make sure that you enter the actual start date for all started
activities and finish date for all activities that are 100%
completed. All *_NEW_* actual start and finish dates *MUST
BE* within the current reporting period.
4. Do *NOT *change the actual start dates if they are already in the
spreadsheet – EVMS does not allow changing the past. If the actual
start date was entered incorrectly in the previous month just leave
it as it is.
5. Do *NOT* enter dates after October 31, 2022,  in *actual*
start/finish dates (columns M and N); this creates errors in P6.
6. Do *NOT* decrease the percent complete in column L.
7. Do *NOT* write any notes in the spreadsheet. If you want to add a
comment use column Y.
8. Do *NOT* change the formatting of the cell once you edit it.  The
spreadsheet will automatically highlight the change in yellow.
*_Additional Note: _*

If progress was made on future activities that are not in the status sheet you can contact your project controls specialist and ask for her help with statusing the activities directly in P6.

Please complete the October status update by *Thursday*, *October27^th *.

We expect the L2 managers and deputies will notify us (Penka,  Carrie, Jenn, Rhoumela, Rosemarie) as soon as the status of their system is complete.

Thank you,

Rosemarie

Rosemarie D. Smith

U.S. ATLAS HL-LHC Upgrade Project

Brookhaven National Laboratory
Physics Department/Omega Group
Office: 631.344.3743
rsmith2 AT bnl.gov <mailto:rsmith2 AT bnl.gov>
cid:image001.png AT 01D88188.08BCB5B0
Twitter <https://urldefense.com/v3/__https://twitter.com/BrookhavenLab__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95POXjJwh7Q$ > | Facebook <https://urldefense.com/v3/__https://www.facebook.com/brookhavenlab__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PNHCLwXqQ$ > | Instagram <https://urldefense.com/v3/__https://www.instagram.com/brookhavenlab/__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PMix-Jhjg$ > | LinkedIn <https://urldefense.com/v3/__https://www.linkedin.com/company/brookhavenlab/__;!!P4SdNyxKAPE!CWLojzLKKVl-t10uAL5F3xQDTYtGueU9Pouc-FsNsqsGVh8y9V3FwKvaF3lOc0UcZpLCi93KCMloUGgBgTcGzyoMTADCfvz6pvs95PPsjsKFIA$ >
_______________________________________________
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l



Archive powered by MHonArc 2.6.24.

Top of Page