usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] August 2023 Status Sheets
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] August 2023 Status Sheets
- Date: Fri, 25 Aug 2023 11:14:40 -0400
A reminder that these are due today (and thanks to Hao, who has already completed them).
John
On 8/21/23 7:22 PM, John Parsons wrote:
Hi all,
It is monthly status and technical bullets time again. Please take care of both by COB on Friday.
Thanks,
John
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] August 2023 Status Sheets
Date: Mon, 21 Aug 2023 22:14:58 +0000
From: Smith, Rosemarie <rsmith2 AT bnl.gov>
To: Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
Good afternoon:
*If you need help, please DO NOT reply to the mailing list*
The Gantt Charts for each subsystem has been uploaded in *DocDB 976*. Please make sure to look over them while statussing the activities.
Status sheets for August are now available in google docs:
*Please note: The activities with baseline start dates in the past are highlighted in orange so you can see how this will impact your monthly performance.*
* *6.01 Pixels: *
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1dv6WLctJnIPsT_AhFb36-Gz4HiOQnK2TQxze6TSsmEI/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkKd8l8fcw$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1dv6WLctJnIPsT_AhFb36-Gz4HiOQnK2TQxze6TSsmEI/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkKd8l8fcw$
>
* *6.02 Strips*:
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1oMUgOG4A7lLWSEYyah_KtW9OHChi1vRLx28hwzA7WEw/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkJtmOmJww$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1oMUgOG4A7lLWSEYyah_KtW9OHChi1vRLx28hwzA7WEw/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkJtmOmJww$
>
* *6.03 Global Mechanics: *
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1a6fzuU5iBOrALHwUCowt2McN3R7C6rVQkIjlDZEQDro/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkLTQT8wgg$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1a6fzuU5iBOrALHwUCowt2McN3R7C6rVQkIjlDZEQDro/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkLTQT8wgg$
>
* *6.04 Lar:*
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1b6DiG2Q5DlndpVGdUFXkVa8sI_Ox6oiKioVVlglFT4I/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkKfR2aSqQ$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1b6DiG2Q5DlndpVGdUFXkVa8sI_Ox6oiKioVVlglFT4I/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkKfR2aSqQ$
>
* *6.05 Tiles:*
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1dgZsxehBccAqQfwKzMC-N8CuwJa3SK1mXOfOry6h0H0/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkKvDazN9g$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1dgZsxehBccAqQfwKzMC-N8CuwJa3SK1mXOfOry6h0H0/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkKvDazN9g$
>
* *6.06 Muons:*
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1ikqgXcdLmrbFUal8Eo1lrJCLNus5c8iPFMLuEXrST2g/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkIj8azUqg$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1ikqgXcdLmrbFUal8Eo1lrJCLNus5c8iPFMLuEXrST2g/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkIj8azUqg$
>
* *6.07 DAQ: *
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/10oWSbH82wu8ZmuaXIoCWYVh2CHtOlqiDhWxcdpe1Uq8/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkK6yT8PkQ$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/10oWSbH82wu8ZmuaXIoCWYVh2CHtOlqiDhWxcdpe1Uq8/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkK6yT8PkQ$
>
* *6.08 Trigger: *
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1sj6-jelKKop5Ei2QPVzK3yDYN5M1UsyFO5npiogRSGs/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkIIjT-8bg$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1sj6-jelKKop5Ei2QPVzK3yDYN5M1UsyFO5npiogRSGs/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkIIjT-8bg$
>
* *6.11 Installation & Integration:*
https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1wau_BatlcPPycw-luZSB4NQ6qw4nvap5MZI12VYlTR0/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkJ2lhdEEQ$
<https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1wau_BatlcPPycw-luZSB4NQ6qw4nvap5MZI12VYlTR0/edit?usp=sharing__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkJ2lhdEEQ$
>
Please remember to update the status online – DO NOT download the files.
The reports contain activities for August 2023 ~ January 2024. You can filter for your CAM name in column D.
**** PLEASE NOTE THE FOLLOWING INSTRUCTIONS IN FILLING OUT YOUR STATUS SHEETS: ****
1. Please provide the status in columns L, M, N, O, and S. Make sure
you provide the **Expected Finish** date (column O) for all
*activities in progress*. This is important for us to re-calculate
EAC, the float, and the critical path.
2. The remaining units are calculated based on the original duration of
the activity and the percent complete. Please provide **Units to
Complete* in column S* for activities in progress. It is if you
expect to use more or less labor for a specific task to be completed
or the cost for material/travel is different than originally
planned. Column T shows Total Cost per resource from P6. Columns U
(Remaining Cost based on the remaining units from P6), V (Updated
Remaining Cost, also called ETC or Estimate-to-Complete), W (EAC or
Estimate at Complete, calculated based on updated units) and X
(Delta EAC minus baseline cost) are formula fields that provide
calculations on how the cost changes when the Remaining Units are
adjusted.
3. Make sure that you enter the actual start date for all started
activities and finish date for all activities that are 100%
completed. All *_NEW_* actual start and finish dates *MUST
BE* within the current reporting period.
4. Do *NOT *change the actual start dates if they are already in the
spreadsheet – EVMS does not allow changing the past. If the actual
start date was entered incorrectly in the previous month just leave
it as it is.
5. Do *NOT* enter dates after August 31, 2023, in *actual*
start/finish dates (columns M and N); this creates errors in P6.
6. Do *NOT* decrease the percent complete in column L.
7. Do *NOT* write any notes in the spreadsheet. If you want to add a
comment use column Y.
8. Do *NOT* change the formatting of the cell once you edit it. The
spreadsheet will automatically highlight the change in yellow.
*__*
*_Additional Note: _*
If progress was made on future activities that are not in the status sheet you can contact your project controls specialist and ask for her help with statussing the activities directly in P6.
Please complete the August Status updates by *_Monday, August 28^th _. *
We expect the L2 managers and deputies will notify Rosemarie, as soon as the status of their system is complete.
Thank you,
Rosemarie
Rosemarie D. Smith
U.S. ATLAS HL-LHC Upgrade Project
Brookhaven National Laboratory
Physics Department, Bldg. 510
PO Box 5000
Upton, NY 11973 -5000
Office: 631.344.3743
rsmith2 AT bnl.gov <mailto:rsmith2 AT bnl.gov>
cid:image001.png AT 01D88188.08BCB5B0
Twitter <https://urldefense.com/v3/__https://twitter.com/BrookhavenLab__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkJmoMXarQ$ > | Facebook <https://urldefense.com/v3/__https://www.facebook.com/brookhavenlab__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkLF_TXxSA$ > | Instagram <https://urldefense.com/v3/__https://www.instagram.com/brookhavenlab/__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkIULcZlZQ$ > | LinkedIn <https://urldefense.com/v3/__https://www.linkedin.com/company/brookhavenlab/__;!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkIa8KnSHw$ >
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!Ge12O_RAQJfg46XjTcwU8cIyWKEyPSsaL3eGdx3grfCqaPS1Yw96R6iULBUHjw9nTY4mvqXFe2EN9ikeJTHrrb4Y5PjtlbDy2XGmtkIc784tNg$
______________________________________________________________________
-
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] August 2023 Status Sheets,
John Parsons, 08/21/2023
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] August 2023 Status Sheets, John Parsons, 08/25/2023
Archive powered by MHonArc 2.6.24.