Hi all,
I see below that Andy has submitted his VAR for November (thanks). A reminder to Tim and I that the deadline is tomorrow. @Tim, please take care of yours asap today, since I need it before I can write my L2 VAR.
Thanks,
John
-------- Forwarded Message --------
Subject: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] November VARs
Date: Thu, 19 Dec 2024 09:28:00 -0800
From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
Reply-To: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Hello all,
Please remind your teams to file their variance reports today. The deadline is tomorrow and many are missing (6.4, 6.4.1, 6.4.2, 6.5.4, 6.6.4, 6.8.1, 6.8.4). Below are comments on those that have been filed.
Best,
Gustaaf
-6.4.3: I have approved, but presumably at some point the expensive LASPs and LASP test stands will be bought? Something to consider for next month.
-6.6: I have approved (but note that for the CSM we’ll just have to carry the variance, as most of that is in the past)
-6.6.3: I have approved -6.6.5: I have approved (but maybe next month say something about the BCP in the corrective action here as well)
-
[[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] November VARs,
John Parsons, 12/19/2024
- Re: [[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] November VARs, Timothy Robert Andeen, 12/19/2024
Archive powered by MHonArc 2.6.24.