[[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2deputymgmt-doe-l] ] DOE risk review
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2deputymgmt-doe-l] ] DOE risk review
- Date: Tue, 19 Aug 2025 16:37:59 -0400
-------- Forwarded Message --------
Subject: Re: [[Usatlas-hllhc-l2deputymgmt-doe-l] ] DOE risk review
Date: Tue, 19 Aug 2025 19:46:29 +0000
From: Reinhard Schwienhorst (via usatlas-hllhc-l2deputymgmt-doe-l Mailing List) <usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov>
Reply-To: Reinhard Schwienhorst <reinhard.schwienhorst AT cern.ch>
To: usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov>
CC: usatlas-hllhc-management-l AT lists.bnl.gov <usatlas-hllhc-management-l AT lists.bnl.gov>
Dear DOE L2s and Deputy L2s,
And while you’re checking the risk registers, please also take a quick look at the IIC risk register, version 4.1,
https://atlas-hllhc.docdb.bnl.gov/0001/000196/116/Risk-Register_IIC_v4.1.xlsx <https://atlas-hllhc.docdb.bnl.gov/0001/000196/116/Risk-Register_IIC_v4.1.xlsx >, just to make sure that there aren't any items that are obviously out-of-date or otherwise incorrect.
Thanks,
Hal and Reinhard
On Aug 19, 2025, at 12:01 PM, Reinhard Schwienhorst <reinhard.schwienhorst AT cern.ch> wrote:
Dear DOE L2s and Deputy L2s,
In preparation for running the DOE risk simulation this September, we will review the current risk register. We will do that offline, as a light-weight risk workshop, and also discuss (as necessary) at the CCB next week. Please review the current risk register, focusing on updates since the December risk workshop. Changes that go along with changes in P6 should have been implemented as we go along, but you might have additional changes to make. Please let me know of any of the following:
- Updating the task affected so that all tasks associated with risks are in the future.
- New risks that might have come up over the past 3 months, or issues that are worrying you these days.
- Large changes in probability or cost/duration uncertainty.
The current risk register in docDB (#196) is v95, and the supply chain risk register is v19:
https://atlas-hllhc.docdb.bnl.gov/0001/000196/116/Risk-Register_v95.xlsx <https://atlas-hllhc.docdb.bnl.gov/0001/000196/116/Risk-Register_v95.xlsx >
https://atlas-hllhc.docdb.bnl.gov/0001/000196/116/Risk-Register_Supply-Chain_v19.xlsx <https://atlas-hllhc.docdb.bnl.gov/0001/000196/116/Risk-Register_Supply-Chain_v19.xlsx >
In case there are changes, please prepare updated versions of these registers with updated cells highlighted. If nothing has changed, please send me a brief email indicating so. We will review the updates at the CCB meeting next week, August 26.
Any issues, please let me know.
Reinhard, on behalf of your friendly PO
-
[[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2deputymgmt-doe-l] ] DOE risk review,