Dear All,
Below please find the minutes from our eRHIC IR Design meeting that
was held on Friday, 10/5/2018. Please note that our next meeting will be
on Friday October 19th, starting at 2:30 pm.
Greetings,
Bill
Minutes from the eRHIC IR Design meeting held on 10/5/18
---------------------------------------------------------------------------------
* We started with a brief discussion of the agenda for the meeting.
* We started with a verbal update by Doug on the integration issues in the IR region.
- Recent iterations with Stephen
- Had to move IR towards the inside of the RHIC ring by 1 m. Has now done so.
- Still in progress
- The current configuration includes:
- 1 m radial move of the IR towards inside of RHIC ring.
- 10 mr rotation of the entire IR design configuration about a vertical axis through the collision point.
- 25 mr crossing angle for the beams.
- Looks promising.
- Next there needs to be an update from Guillaume on the Hadron ring.
- Question whether this integration issue has been looked at for both IR 6 and IR 8?
- Not clear, but likely this has only been looked at for IR 6.
- Need to determine what the constraints are for sPHENIX to be an eRHIC detector.
* Simulation Update (verbal) from Elke:
- Looked at whether nuclei can be detected if only one nucleon is knocked out.
- getting setup for this study
- looking into coherent vs incoherent scattering
- Nothing yet for the new IR design. Waiting to get the next complete IR design.
- Working with Christoph to get things ready for the upcoming EIC Collaboration mtg at the end of October.
- Bob will give the IR talk at the JLAB mtg.
* Brief discussion on pCDR costs.
* Brief discussion on the MADX files/software and its limitations.
* Walk through Bob's latest IR design update (version 8a): File attached.
- Slide #6:
- Boxes represent the magnet apertures
- "tiling" the magnets (offsetting along beam lines e and hadron magnets) gives much more geopmetric space between the e and hadron lines.
- Bob and Brett will discuss ability to change the B1 field strength with Guillaume.
- Slide #9:
- Tilt angles are given with respect to the hadron beam.
- Slide #22:
- Rear side for Hadron beams
- Blue = Y divergence
- Red = X divergence
- dotted = scaled X
>>>>> Bob proposes that the apertures shown on Slide #22 is accepted as a "constraint" on the IR design. "Estimate" of the worst case. <<<<
- Slide #25:
- 22 mr listed should be 25 mr
- End of presentation.
* Discussion:
- It was decided (prior to today's meeting) that Brett would be in chanrge of the cost estimate for the IR magnets.
- The proposal is to take Bob's latest design, version 8a.
* Next meeting:
- In two weeks, which means on Friday, October 19th.
- Agenda is to have dry runs of the presentations that will be shown at the EIC Collaboration meeting.
- Elke will (and did) arrange for a dial in. Info. is below:
To join the Meeting:
To join via Room System:
Video Conferencing System: bjn.vc -or-199.48.152.152
Meeting ID : 100271362
To join via phone :
1) Dial:
+1.408.740.7256 (US (San Jose))
+1.888.240.2560 (US Toll Free)
+1.408.317.9253 (US (Primary, San Jose))
(see all numbers -
http://bluejeans.com/numbers)
2) Enter Conference ID : 100271362
|
Attachment:
1809-IR-update-v8a.pdf
Description: 1809-IR-update-v8a.pdf
-
[E-rhic-ir-l] Minutes from the eRHIC IR Design meeting held on October 5, 2018.,
Christie, William, 10/18/2018
- Re: [E-rhic-ir-l] Minutes from the eRHIC IR Design meeting held on October 5, 2018., Alexander Bazilevsky, 10/18/2018
Archive powered by MHonArc 2.6.24.