e-rhic-ir-l AT lists.bnl.gov
Subject: E-rhic-ir-l mailing list
List archive
[E-rhic-ir-l] Minutes from the eRHIC IR Design meeting held on October 5, 2018.
- From: "Christie, William" <christie AT bnl.gov>
- To: "e-rhic-ir-l AT lists.bnl.gov" <E-rhic-ir-l AT lists.bnl.gov>
- Subject: [E-rhic-ir-l] Minutes from the eRHIC IR Design meeting held on October 5, 2018.
- Date: Thu, 18 Oct 2018 21:25:48 +0000
Dear All, Below please find the minutes from our eRHIC IR Design meeting that was held on Friday, 10/5/2018. Please note that our next meeting will be on Friday October 19th, starting at 2:30 pm. Greetings, Bill Minutes from the eRHIC IR Design meeting held on 10/5/18 --------------------------------------------------------------------------------- * We started with a brief discussion of the agenda for the meeting. * We started with a verbal update by Doug on the integration issues in the IR region. - Recent iterations with Stephen - Had to move IR towards the inside of the RHIC ring by 1 m. Has now done so. - Still in progress - The current configuration includes: - 1 m radial move of the IR towards inside of RHIC ring. - 10 mr rotation of the entire IR design configuration about a vertical axis through the collision point. - 25 mr crossing angle for the beams. - Looks promising. - Next there needs to be an update from Guillaume on the Hadron ring. - Question whether this integration issue has been looked at for both IR 6 and IR 8? - Not clear, but likely this has only been looked at for IR 6. - Need to determine what the constraints are for sPHENIX to be an eRHIC detector. * Simulation Update (verbal) from Elke: - Looked at whether nuclei can be detected if only one nucleon is knocked out. - getting setup for this study - looking into coherent vs incoherent scattering - Nothing yet for the new IR design. Waiting to get the next complete IR design. - Working with Christoph to get things ready for the upcoming EIC Collaboration mtg at the end of October. - Bob will give the IR talk at the JLAB mtg. * Brief discussion on pCDR costs. * Brief discussion on the MADX files/software and its limitations. * Walk through Bob's latest IR design update (version 8a): File attached. - Slide #6: - Boxes represent the magnet apertures - "tiling" the magnets (offsetting along beam lines e and hadron magnets) gives much more geopmetric space between the e and hadron lines. - Bob and Brett will discuss ability to change the B1 field strength with Guillaume. - Slide #9: - Tilt angles are given with respect to the hadron beam. - Slide #22: - Rear side for Hadron beams - Blue = Y divergence - Red = X divergence - dotted = scaled X >>>>> Bob proposes that the apertures shown on Slide #22 is accepted as a "constraint" on the IR design. "Estimate" of the worst case. <<<< - Slide #25: - 22 mr listed should be 25 mr - End of presentation. * Discussion: - It was decided (prior to today's meeting) that Brett would be in chanrge of the cost estimate for the IR magnets. - The proposal is to take Bob's latest design, version 8a. * Next meeting: - In two weeks, which means on Friday, October 19th. - Agenda is to have dry runs of the presentations that will be shown at the EIC Collaboration meeting. - Elke will (and did) arrange for a dial in. Info. is below: To join the Meeting: To join via Room System:
Video Conferencing System: bjn.vc -or-199.48.152.152
Meeting ID : 100271362
To join via phone :
1) Dial:
+1.408.740.7256 (US (San Jose))
+1.888.240.2560 (US Toll Free)
+1.408.317.9253 (US (Primary, San Jose))
(see all numbers -
http://bluejeans.com/numbers)
2) Enter Conference ID : 100271362
|
Attachment:
1809-IR-update-v8a.pdf
Description: 1809-IR-update-v8a.pdf
-
[E-rhic-ir-l] Minutes from the eRHIC IR Design meeting held on October 5, 2018.,
Christie, William, 10/18/2018
- Re: [E-rhic-ir-l] Minutes from the eRHIC IR Design meeting held on October 5, 2018., Alexander Bazilevsky, 10/18/2018
Archive powered by MHonArc 2.6.24.