  • From: "Ilardo, Matthew" <milardo AT bnl.gov>
  • To: "Lenz, Michael D" <mlenz AT bnl.gov>
  • Cc: "La Bounty, James" <labounty AT bnl.gov>, "sphenix-emcal-l AT lists.bnl.gov" <sphenix-emcal-l AT lists.bnl.gov>, "Lenz, William" <wlenz AT bnl.gov>
  • Subject: Re: [Sphenix-emcal-l] EMCal Sector 0 dryfit blocks
  • Date: Mon, 20 May 2019 15:36:49 +0000

I have all the parts processed, what surfaces are most important? Would you like to come here around 2 to go over the report you would like?

 

bcard

 

From: Michael Lenz <mlenz AT rcf.rhic.bnl.gov>
Sent: Monday, May 20, 2019 11:10 AM
To: Ilardo, Matthew <milardo AT bnl.gov>
Cc: Sickles, Anne M <sickles AT illinois.edu>; Morrison, David <morrison AT bnl.gov>; Stoll, Sean <stoll AT bnl.gov>; Lenz, Michael D <mlenz AT bnl.gov>; La Bounty, James <labounty AT bnl.gov>; Lenz, William <wlenz AT bnl.gov>; sphenix-emcal-l AT lists.bnl.gov; O'Brien, Edward <eobrien AT bnl.gov>
Subject: Re: [Sphenix-emcal-l] EMCal Sector 0 dryfit blocks

 

Hi Matt,    I know you said processing the survey results was very labor intensive, but as you can read below, we are at a critical point in our assembly process. If you are not able to provide the survey results by this afternoon, please let us know asap. We need to move forward !  Thank you !  Mike

PS   Does processing this type of survey usually take this long (2 weeks) ?   We would need to know this for future requests !

On 5/20/2019 9:59 AM, Sickles, Anne M wrote:

Dear Sean,

 

I agree it looks great (and thanks for all the pictures).  Do you know when you will hear back about the survey?  Is it possible you’ll hear before the target to make a decision on the gluing tomorrow afternoon as we discussed in the EMCal meeting on Friday?

 

Best,

Anne



On May 20, 2019, at 8:36 AM, David Morrison <morrison AT bnl.gov> wrote:

 

That looks fantastic!

Dave

On 5/17/19 4:33 PM, Sean Stoll wrote:

All,

 We did a dryfit of Sector 0 with 96 blocks this afternoon.

(A few of the blocks had wet optical couplant, so we used some spares
for the photo.)

I think all looks good. We are still waiting on the survey numbers for
the sawteeth. So maybe we want to hold off on epoxying things in place
until we see those, but we didn't see any obvious problems with the
fitting that would indicate significant dimensional issues.

"Good work" to all who contributed to the effort.

Sean


-- 
David Morrison  Brookhaven National Laboratory  phone: 631-344-5840
               Physics Department, Bldg 510 C    fax: 631-344-3253
                         Upton, NY 11973-5000  email: 
dave AT bnl.gov

_______________________________________________
sPHENIX-EMCal-l mailing list
sPHENIX-EMCal-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/sphenix-emcal-l

 




Archive powered by MHonArc 2.6.24.

Top of Page