Hello
The original conversation that I had with Brian Streckenbach was about moving
interior shielding blocks behind hi-bay door 15. The reason behind this was
to open up more square footage for storage of the outer hcal sectors.
It appears now that CA-D is open to removing much more shielding than
originally discussed, which I agree is a good thing, but will require quite a
bit more planning. I will reach out to Brian on Monday and we can start to
formulate a plan moving forward. The best case scenario would be zero
disruption of electrical power so the HCAL group can continue with testing
the sector electronics. I will keep all parties involved well informed of
the plan we develop moving forward.
If anyone has any specific concerns, feel free to email me directly and I can
see to it that we address them appropriately.
Chris Pontieri
cpontieri AT bnl.gov
631-344-5038
-----Original Message-----
From: sPHENIX-HCal-l <sphenix-hcal-l-bounces AT lists.bnl.gov> On Behalf Of
Stefan Bathe
Sent: Friday, December 20, 2019 5:45 PM
To: Haggerty, John <haggerty AT bnl.gov>
Cc: sphenix-hcal-l AT lists.bnl.gov
Subject: Re: [Sphenix-hcal-l] More space in 912
Hi John, All,
Thanks for the info!
Oops, really? When I last discussed this with Chris P. on Tuesday, the plan
was to propose to Brian to move only the shielding blocks that don’t have
utility lines running on top. So I didn’t anticipate this. Maybe Chris
could send an explanation to the list why the power loss might be an
implication of this? (Sorry, Chris, I had to miss yesterday’s planning
meeting due to end-of-semester business.) If that’s really the case, this
work would really have to be well coordinated in order not to impact us too
much.
Regards,
Stefan
--
---------------------------------------------------------------------------------
Stefan Bathe
Professor of Physics
Baruch College, CUNY
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
> On Dec 20, 2019, at 4:52 PM, John Haggerty <haggerty AT bnl.gov> wrote:
>
> I thought I better report this to the HCAL group before all the eggnog
> makes me forget about it:
>
> I didn't attend the weekly planning meeting yesterday, but Carter and Frank
> came by afterward to say that Brian is looking into the feasibility of
> expanding the floor space in 912 for HCAL assembly. That's good! At least I
> think so, but they warned me that part of the work may take power away from
> our test racks for a few weeks to a month depending on how the work is
> organized. That's not great, because we still have more development to do
> in the testing, but it's probably better to take the interruption when
> we're not swamped with sectors to test.
>
> In any case, I thought the HCAL group should hear about these deliberations
> so we can decide what we want to do about it with 2020 vision.
>
> Have a good holiday!
>
> --
> John Haggerty
> email: haggerty AT bnl.gov
> cell: 631 741 3358
> _______________________________________________
> sPHENIX-HCal-l mailing list
> sPHENIX-HCal-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/sphenix-hcal-l
_______________________________________________
sPHENIX-HCal-l mailing list
sPHENIX-HCal-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/sphenix-hcal-l
-
[Sphenix-hcal-l] More space in 912,
John Haggerty, 12/20/2019
-
Re: [Sphenix-hcal-l] More space in 912,
Stefan Bathe, 12/20/2019
-
Re: [Sphenix-hcal-l] More space in 912,
Pontieri, Chris, 12/20/2019
-
Re: [Sphenix-hcal-l] More space in 912,
Eric Mannel, 12/20/2019
- Re: [Sphenix-hcal-l] More space in 912, Biggs, John C, 12/21/2019
-
Re: [Sphenix-hcal-l] More space in 912,
Eric Mannel, 12/20/2019
-
Re: [Sphenix-hcal-l] More space in 912,
Pontieri, Chris, 12/20/2019
-
Re: [Sphenix-hcal-l] More space in 912,
Stefan Bathe, 12/20/2019
Archive powered by MHonArc 2.6.24.