sphenix-magnet-l - Re: [Sphenix-magnet-l] sPHENIX Magnet meeting on Feb. 3 at 1:30 pm in the 902 conference room

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: "Yip, Kin" <kinyip AT bnl.gov>
  • To: "Giannotti, Paul" <gia AT bnl.gov>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Subject: Re: [Sphenix-magnet-l] sPHENIX Magnet meeting on Feb. 3 at 1:30 pm in the 902 conference room
  • Date: Wed, 3 Feb 2016 01:50:16 +0000

Thanks a lot, Paul !   Nice pictures … Even the floor seems cleaner than a couple hours ago when I was there J

 

Kin

 

From: Giannotti, Paul
Sent: Tuesday, February 02, 2016 8:44 PM
To: Yip, Kin <kinyip AT bnl.gov>; sphenix-magnet-l AT lists.bnl.gov
Subject: Re: [Sphenix-magnet-l] sPHENIX Magnet meeting on Feb. 3 at 1:30 pm in the 902 conference room

 

Here are some photos of the pre-walkthrough condition taken an hour ago.

 

Kin,

 

Defective Strain Gauges:

  1. TS03 (bad pin M on connector plug J4
  2. TS82 (bad connector pin j on connector plug J5)
  3. TS32 and TS92 (likely bad connections on Valve Box J6)
  4. TS80 (likely shorted at sensor itself)

 

Tie Rod temperature sensors TT01, TT02, TT03, TT04, TT05 are now wired into the Magnet Power Control & Data Acquisition Rack (not Cryo Rack).

 

All Power & Control Racks inspected (EEI) and bar code stickers attached.

 

Regards,

 

Paul

 

From: <sphenix-magnet-l-bounces AT lists.bnl.gov> on behalf of "Yip, Kin" <kinyip AT bnl.gov>
Date: Tuesday, February 2, 2016 at 3:06 PM
To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
Subject: [Sphenix-magnet-l] sPHENIX Magnet meeting on Feb. 3 at 1:30 pm in the 902 conference room

 

Just to remind you of our meeting tomorrow (Wed.) Jan. 27 at 1:30 pm in the 902 conference room.

 

--- The roughing pump has been turned on since yesterday late afternoon/evening.    I saw Paul Orfin and his guys as well as

Rich Meier are making the final connections.

 

--- Paul Giannotti claimed that he’s just needed another hour.

 

--- I’m looking for D. Phillips to put his barrier for the power lead (on the platform), put up the startle sign and anchor things properly.

 

 

Agenda/powerpoint (https://indico.bnl.gov/conferenceDisplay.py?confId=1728):

 

*       Scheduling towards the cool-down/low-field test

*      Strain Gauge Connections ?

*      Pressure test/leak check (which is to be used for step 200 in the pre-test inspection Traveler) ?

*      Dave: Barrier for power lead/Steel anchored properly

*      Hypot/Impulse test on Thursday/Friday ?

*      Cut from ERL cryo line and welding ?

*      DAQ ready ?

*      Cool-down next week

*      AOB

Þ “Safety walkthrough” at 2:30 pm (Bldg. 912)

 