sphenix-magnet-l - [Sphenix-magnet-l] Richard is done with the valves and he and Paul Giannotti are said to be ready by the end of Monday

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: Kin Yip <kinyip AT bnl.gov>
  • To: "Ceruti, Raymond B" <rayc AT bnl.gov>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>, "Meier, Richard" <remeier AT bnl.gov>
  • Subject: [Sphenix-magnet-l] Richard is done with the valves and he and Paul Giannotti are said to be ready by the end of Monday
  • Date: Thu, 9 Nov 2017 16:50:34 -0500

Hi Ray,

A couple hours ago, when Paul Giannotti and I walked around in 912, we talked to Richard Meier.  Richard told me that he's done with
the valve connections and he's working on the other cryo connections.  When I asked him when he'd be ready for you to close the doghouse,
he said sometime on Monday.   Paul claims that he will be not be later than Richard :-)

So, they may be done by the end of Monday and you may be able to close the doghouse starting on Tuesday.   Please check with Richard Meier and Paul Giannotti. 

Please send us an email if you're done with closing the doghouse.   If I don't hear anything early next week, I'll shoot you guys emails from somewhere in Asia.