- [Sphenix-magnet-l] MCM Cables are all laid on trays. You may install your signal cables, Yip, Kin, 11/01/2017
-
[Sphenix-magnet-l] Roof Steel installed ... Testing Quench-Detection System ...,
Yip, Kin, 11/02/2017
-
Re: [Sphenix-magnet-l] Roof Steel installed ... Testing Quench-Detection System ...,
EdwardOBrien, 11/02/2017
- Re: [Sphenix-magnet-l] Roof Steel installed ... Testing Quench-Detection System ..., Yip, Kin, 11/02/2017
-
Re: [Sphenix-magnet-l] Roof Steel installed ... Testing Quench-Detection System ...,
EdwardOBrien, 11/02/2017
- [Sphenix-magnet-l] Cryo hopes to do pressure test next week ... should be ready for Nov. 17 safety walkthrough ..., Kin Yip, 11/03/2017
- [Sphenix-magnet-l] Nov. 13-28 (vacation), Kin Yip, 11/06/2017
- [Sphenix-magnet-l] electrical/hypot tests are done --- voltage taps connected to the resistor board, Kin Yip, 11/07/2017
- [Sphenix-magnet-l] Reminder of today's sPHENIX biweekly meeting at 1:30 pm (902A conference room), Yip, Kin, 11/08/2017
-
[Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room,
Yip, Kin, 11/08/2017
-
Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room,
Phillips, David B, 11/14/2017
-
Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room,
EdwardOBrien, 11/14/2017
- Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room, Phillips, David B, 11/14/2017
- Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room, EdwardOBrien, 11/14/2017
-
Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room,
EdwardOBrien, 11/14/2017
-
Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room,
Phillips, David B, 11/14/2017
- [Sphenix-magnet-l] Richard is done with the valves and he and Paul Giannotti are said to be ready by the end of Monday, Kin Yip, 11/09/2017
- [Sphenix-magnet-l] Nov. 20: ASSRC Walk tthrough of s-PHENIX, Cirnigliaro, Peter P, 11/14/2017
- [Sphenix-magnet-l] network addresses ... Ray to close doghouse on Thursday ... more plan from Dave, Yip, Kin, 11/14/2017
- Re: [Sphenix-magnet-l] network addresses, Yip, Kin, 11/14/2017
- [Sphenix-magnet-l] Pressure test is complete ... doghouse to be closed, Yip, Kin, 11/15/2017
- [Sphenix-magnet-l] new doghouse was Closed, Yip, Kin, 11/16/2017
-
Re: [Sphenix-magnet-l] Start insulating vacuum pump down,
Yip, Kin, 11/17/2017
-
Re: [Sphenix-magnet-l] Start insulating vacuum pump down,
Anerella, Michael D, 11/17/2017
- Re: [Sphenix-magnet-l] Start insulating vacuum pump down, Yip, Kin, 11/17/2017
-
Re: [Sphenix-magnet-l] Start insulating vacuum pump down,
Mills, James A, 11/17/2017
- Re: [Sphenix-magnet-l] Start insulating vacuum pump down, Anerella, Michael D, 11/17/2017
-
Re: [Sphenix-magnet-l] Start insulating vacuum pump down,
Anerella, Michael D, 11/17/2017
- [Sphenix-magnet-l] PS Test Schedule, Phillips, David B, 11/17/2017
- [Sphenix-magnet-l] FW: Question about the cryostat support jacks, Mills, James A, 11/20/2017
- [Sphenix-magnet-l] Fw: sPHENIX flange leak, Yip, Kin, 11/20/2017
-
Re: [Sphenix-magnet-l] sPHENIX Magnet Vacuum Leak Repair,
Yip, Kin, 11/21/2017
- Re: [Sphenix-magnet-l] sPHENIX Magnet Vacuum Leak Repair, Than, Yatming (Roberto), 11/21/2017