sphenix-magnet-l AT lists.bnl.gov
Subject: sPHENIX discussion of the superconducting solenoid
List archive
Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room
- From: EdwardOBrien <eobrien AT bnl.gov>
- To: "Phillips, David B" <phillips AT bnl.gov>, "Yip, Kin" <kinyip AT bnl.gov>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Subject: Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room
- Date: Tue, 14 Nov 2017 17:33:33 -0500
Hi Dave, One question. Does Pablo need to finish the short circuit test before Frank does the DC hook-up at the valve box? Ed On 11/14/2017 5:29 PM, Phillips, David
B wrote:
sPHENIX Magnet work which I am aware of for the next 2 weeks, please correct me as necessary & see how this fits in with other work:
11/15-16 Survey Group/Jon H/M-Tec - final tightening of the radial & axial cryostat supports, clean inside magnet. 11/17 Carter install the magnetic measurement frame. 11/20 ESRC walkthrough 10:00. 11/20-? Install the steel end wall (don’t know if rigging & tec’s will be available with the holiday next week). 11/15? Frank start DC hook-up at Valvebox (Paul O. did the valvebox lead heater get installed today?). 11/20? Set-up for the short circuit test for Pablo. 11/27? Start magnet cooldown
From:
sPHENIX-magnet-l
[mailto:sphenix-magnet-l-bounces AT lists.bnl.gov]
On Behalf Of Yip, Kin
https://indico.bnl.gov/conferenceDisplay.py?confId=3773
1. Yesterday, Sonny Dimaiuta finished electrical/hypot tests and connected the voltage tap cables down to the lower platform. It’s the job of Carl/Fred Orsatti need to connect from there to their Rack. I show Fred whether the voltage-tap cables were in 922 and also from where to where that he needs to pull the cables in 912. He apparently took the voltage-tap cables to 912 since then. 2. Ray Ceruti can close up the doghouse as soon as Richard Meier and Paul Giannotti/Frank Toldo declare that their connections are good. Richard Meier (Cryo) is busy with connecting the signals to control the valves and I urged Tom Tallerico to get Richard to do the doghouse connections as soon as possible. Paul Giannotti promised in the meeting that his strain gauge connections can be done by tomorrow J 3. Cryo group is supposed to do the pressure test this week. But it looks like they’ll probably do the pressure test next Monday. Richard Meier also needs to connect and check out all the cryo connections. 4. Frank Toldo basically finishes terminating the 535 MCM cables this week for dump resistors and power supplies. He’s going to make connections at the doghouse. 5. Jon Hock needs to finish his preparation, ask Carter to install magnetic probes, install his linear pots (2) and close the end-walls. Jon now expects that he finish all these “next week”. 6. P. Rosas needs to do his interlock tests. (etc.) after he connects his signals between his small rack and dump resistor/power supply.
7. Carl and Zeynep have finished the majority of their test and have agreed to move the rack to 912 tomorrow (Nov. 9). There is a PLL issue that they need to solve. Once the rack moved to 912, we need to connect power and network, and then Carl/Zeynep can work on the overall integration and noise etc.
8. This morning, I asked Peter Cirnigliaro to try to schedule the safety walkthrough (as one of the ASSRC check-off items). Nobody in today’s meeting objected to this date for the safety walkthrough. Peter is checking with Deepak about this date and I haven’t heard from Peter yet.
9.
We need to barrier those
leads at the Valvebox, dump resistor and power supply.
Ed O’Brien volunteered Mike Lenz (in PHENIX/PHYSICS) to
help do this job.
_______________________________________________ sPHENIX-magnet-l mailing list sPHENIX-magnet-l AT lists.bnl.gov https://lists.bnl.gov/mailman/listinfo/sphenix-magnet-l |
-
[Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room,
Yip, Kin, 11/08/2017
-
Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room,
Phillips, David B, 11/14/2017
-
Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room,
EdwardOBrien, 11/14/2017
- Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room, Phillips, David B, 11/14/2017
-
Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room,
EdwardOBrien, 11/14/2017
-
Re: [Sphenix-magnet-l] Brief Summary of today's sPHENIX Magnet biweekly meeting at 1:30 pm at 902A conf. room,
Phillips, David B, 11/14/2017
Archive powered by MHonArc 2.6.24.