Skip to Content.
Sympa Menu

sphenix-maps-l - Re: [Sphenix-maps-l] [Sphenix-l] MAPS-based Vertex Detector (MVTX) pre-proposal - v1.2

sphenix-maps-l AT lists.bnl.gov

Subject: sPHENIX MAPS tracker discussion

List archive

Chronological Thread  
  • From: Edward O'Brien <eobrien AT bnl.gov>
  • To: "Ming Liu (ming AT bnl.gov)" <ming AT bnl.gov>, Spencer Klein <srklein AT lbl.gov>, leo greiner <lcgreiner AT lbl.gov>
  • Cc: "sphenix-l AT lists.bnl.gov" <sphenix-l AT lists.bnl.gov>, sphenix-maps-l <sphenix-maps-l AT lists.bnl.gov>, phenix-team <p25henp-l AT lanl.gov>
  • Subject: Re: [Sphenix-maps-l] [Sphenix-l] MAPS-based Vertex Detector (MVTX) pre-proposal - v1.2
  • Date: Wed, 8 Feb 2017 00:09:17 -0600

Hi Ming and Dave,
The BNL engineering is already fully committed
on the sPHENIX scope. I am not sure that the
best place to save MVTX funds is by moving
responsibilities to BNL. Have you looked at this
from a different angle, instead determining what
could be built for $4.9M including overhead,
escalation and contingency. By the way I don't have any
problem assuming that students and postdocs will be available
for QA and testing. Are there other MVTX jobs suitable
for students?

Ed


On 2/2/17 3:43 PM, Ming Liu (ming AT bnl.gov) wrote:
Hi Spencer and all,

You raised the right questions. Here is a reply from Dave Lee this
morning, detailing about the updated cost and schedule to Leo, somehow the
reply didn’t go through the list. Hope this email can help people to
better understand the changes. As we discussed it at LBNL last week, we
are asked to keep the total project cost under $5M.

Cheers,
Ming

――
Hi Leo,
Let me reply and Ming can provide further. As a backdrop I had a long
conversation with Ed O'Brien concerning the MVTX project and strategy.
The cost of new projects with the ONP has implications as to how the
funding route would be. For projects >$5M the project does not go through
the CD process but does become part of the OMB budget process and
therefore is at least a 2 year process. For projects <$5M the project is
funded directly from the ONP without being in the OMB budget process and
thus can be approved internal to the ONP much sooner. By trimming the
budget to less than $5M we hope a much more favorable outcome from the
late February DOE-NP will occur. To achieve these savings we have trimmed
resources across the project by using more uncosted or less expensive
labor, moving some integration tasks to BNL engineers outside of the
project, moving part of the LANL design efforts on global integration to
BNL, reducing LANL hourly rate by using contracted labor, reducing travel
expenses by ~20%, and by reducing some durations so that we meet Ed's
start installation date of 2/2021. Nothing drastic was done to any
activity or procurement cost. Hope this helps
Dave