Hi Ed and Grazyna,
Yes, it is a good idea to have a clean tent with sufficient space for the
half-detector, the overall length is <~ 2.5m, not super large.
We could bring it up at next sPHENIX planning meeting?
Cheers,
Ming
-----
Dr. Ming Xiong Liu
P-3, MS H846
Physics Division
Office: 505.667.7125
Mobile: 505.412.7396
Los Alamos National Laboratory
lanl.gov
<https://www.instagram.com/losalamosnatlab/>
<https://twitter.com/LosAlamosNatLab>
<https://www.linkedin.com/company/los-alamos-national-laboratory/>
<https://www.facebook.com/LosAlamosNationalLab/>
--
On 4/27/21, 4:35 PM, "sPHENIX-MAPS-l on behalf of Grazyna Odyniec"
<sphenix-maps-l-bounces AT lists.bnl.gov on behalf of g_odyniec AT lbl.gov> wrote:
Hi Ming and Ed,
When we build STAR vertex detector, HFT, (also built in LBNL and
transported to BNL), we have had a small "clean room" tent set in the
assembly hall area of STAR. It was meant for the same. And I think it
worked well. There was enough room, that even when STAR detector was
rolled back to the assembly hall, this clean tent was not disturbed.
Can we have a similar arrangement in sPHENIX assembly area ?
best, Grazyna
On 4/27/21 2:38 PM, Edward O'Brien wrote:
> Hi Ming,
> You are bringing up an important issue. We would have to identify
> the space at BNL to do this kind of rework. My best knowledge is
that
> there aren't any unoccupied clean rooms at BNL. If we think that
> we might need one for the MVTX we need to do a little planning
> ahead of time. Thanks.
>
> Ed
>
> On 4/23/21 4:53 PM, Liu, Ming Xiong wrote:
>> Hi Grazyna, Camelia, Yuan, Jo and all,
>>
>> One topic that I didn’t get time to bring up for discussion at
>> today's meeting, and like to ask you all to think about:
>> - what if we need to re-work on the assembled detector at BNL? Will
>> we be ready?
>>
>> From ALICE experience (see the following email), ITS has to rework
>> on the detector assembly several times during the surface
>> commissioning and also at installation.
>> Well they have labs at CERN so it was not a big challenge, it could
>> be different for MVTX.
>>
>> My concern is that whether we can do the similar work at BNL - open
>> up the detector and replaced faulty components, could be cables or
>> sensors etc.
>>
>> Our current plan is to ship the fully tested MVTX half-detectors to
>> BNL early 2022, and we will have several months of time doing
>> pre-installation commissioning, and hope nothing bad happens to the
>> MVTX detectors. BUT, we need to be prepared for the worst, so my
>> question is:
>> - should we also ship all the assembly fixtures to BNL and
>> setup a clean tent so that we can rework on the half-detectors if
>> needed? Or we send the detector back to LBNL to fix?
>> - do the current assembly fixtures and procedure allow us to do
>> such operation at BNL?
>>
>> Cheers,
>> Ming
>> -----
>>
>> Dr. Ming Xiong Liu
>> P-3, MS H846
>> Physics Division
>> Office: 505.667.7125
>> Mobile: 505.412.7396
>> Los Alamos National Laboratory
>> lanl.gov
>>
<https://urldefense.com/v3/__https://www.instagram.com/losalamosnatlab/__;!!P4SdNyxKAPE!SpuK63MdUiHySh3YRBDc8t5WFCK-NoAaRzR1LzQ8fRoOir-Z0eR1IlIevrEmakqfLy6nAhNwEZQ$
>> >
>>
<https://urldefense.com/v3/__https://twitter.com/LosAlamosNatLab__;!!P4SdNyxKAPE!SpuK63MdUiHySh3YRBDc8t5WFCK-NoAaRzR1LzQ8fRoOir-Z0eR1IlIevrEmakqfLy6nBjDlEXM$
>> >
>>
<https://urldefense.com/v3/__https://www.linkedin.com/company/los-alamos-national-laboratory/__;!!P4SdNyxKAPE!SpuK63MdUiHySh3YRBDc8t5WFCK-NoAaRzR1LzQ8fRoOir-Z0eR1IlIevrEmakqfLy6nO_p7X7A$
>> >
>>
<https://urldefense.com/v3/__https://www.facebook.com/LosAlamosNationalLab/__;!!P4SdNyxKAPE!SpuK63MdUiHySh3YRBDc8t5WFCK-NoAaRzR1LzQ8fRoOir-Z0eR1IlIevrEmakqfLy6n34MjMiI$
>> >
>
> _______________________________________________
> sPHENIX-MAPS-l mailing list
> sPHENIX-MAPS-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/sphenix-maps-l
_______________________________________________
sPHENIX-MAPS-l mailing list
sPHENIX-MAPS-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/sphenix-maps-l
-
[Sphenix-maps-l] MVTX commissioning plan .... Possible rework on detector at BNL,
Liu, Ming Xiong, 04/23/2021
-
Re: [Sphenix-maps-l] MVTX commissioning plan .... Possible rework on detector at BNL,
Edward O'Brien, 04/27/2021
-
Re: [Sphenix-maps-l] MVTX commissioning plan .... Possible rework on detector at BNL,
Grazyna Odyniec, 04/27/2021
- Re: [Sphenix-maps-l] MVTX commissioning plan .... Possible rework on detector at BNL, Ming Liu, 04/27/2021
-
Re: [Sphenix-maps-l] MVTX commissioning plan .... Possible rework on detector at BNL,
Grazyna Odyniec, 04/27/2021
-
Re: [Sphenix-maps-l] MVTX commissioning plan .... Possible rework on detector at BNL,
Edward O'Brien, 04/27/2021
Archive powered by MHonArc 2.6.24.