Minutes shift change 2023-04-17
general (Kin)
-----------
- test walk through for operation readiness today
- no new issues
- real walk-through next Monday
evening: Oliver
- nothing
night: Ejiro
INTT (Rachid)
- N and S tested, testing in bore done
DAQ
- nothing
night: Ejiro
- the mouse came back
- Stefan called the building manager today, who will put in a work order for that
day: Virginia
- EMCal South LV was turned on today with cooling (in addition to North)
- but no interlocks yet, so only expert operation
MBD (Mickey)
- after Jimmy cleaned up cables, checked noisy channels, better, but should be fixed up some more
- Mickey cleaned up more, will continue tomorrow
HCal (Virginia)
- paused taking cosmics data until we can sort out issues with data taking
EMCal (Anthony)
- all racks reading out
- now checking cabling in rack room
- also checking out broken packets (checksum errors)
TPOT (Hugo)
- Hugo only coming tomorrow (flight issues)
- plan to work on noise, electronics
TPC (John K)
- Rob gave OK to turn on even number sectors in both North and South
- no interlocks yet, expert only
TPC (John K)
- Rob gave OK to turn on even number sectors in both North and South
- no interlocks yet, expert only
INTT (Rachid)
- N and S tested, testing in bore done
- Steve and Sal were working on cooling interlock system
- will test interlocks tomorrow morning
- Maya updated GUI for LV to be released to shift crew
- today new framework for FELIX
- will start testing at 5:00pm (daily)
MVTX (John H)
MVTX (John H)
- new fibers will later this week
sEPD (Rosi)
- South side frame being installed
- South side frame being installed
- will be surveyed tomorrow
- will install 12 optical fibers now
- other 12 will be installed later this week
- that will be all that goes in for now
DAQ
- see separate DAQ meeting after shift change
Magnet (Kin)
- hipot test
- hipot test
- narrowed problem down to be inside magent
- noticed that vacuum pump wasn’t running, turned pump on, then test successful
- that means current was flowing through gas in magnet
Gas/cooling water (no report)
- Rachid requests nitrogen to protect INTT sensors
Plan of the day
- Rachid requests nitrogen to protect INTT sensors
Plan of the day
- DAQ development
- subsystem testing
-
---------------------------------------------------------------------------------
Stefan Bathe
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
- [Sphenix-run-l] Minutes shift change 2023-04-17, Stefan Bathe, 04/17/2023
Archive powered by MHonArc 2.6.24.