Minutes shift change 2023-04-24

general
—————
- new shift crews, training after this meeting, tomorrow overlap day
- safety walk through at 1:00pm today (Kin)
  - electrical expert:  arc flash sign in all racks, etc
  - fire expert:  scaffolding wood flammable, can be painted by fire retardant paint
- tomorrow morning 7:00am test fit of plug door, no one allowed in IR for that; should be done by 8:00am
- Wednesday morning to Friday:  pole tip door will be closed for test close and magnet power supply work
  - will lose access to bore Tuesday evening/Wednesday morning to Friday
  - use opportunity to test all detectors together:  noise, heat 

evening:  Cameron
- pretty quiet
- had tried to get air out of MVTX lines
- when tried to turn chiller on didn’t respond anymore
- had to replace chiller memory card (SD card)
- deleted log files, put original card back, all good
- wrote up shift crew chiller page on run web page, sub-atmospheric chillers (MVTX, FVTX, TPC, TPOT)
- -> add label to control panels regarding which detector we are looking at
- disconnected for SD card work, caused water leak, alarm

night:  Charles
- only EMCal North and HCal were on
- one chiller had dropped below 1.8 l/min
- instructions to call subsystem expert
- investigating

day:  Sean
- relatively quiet
- put fan on damp spot, cleared up alarm condition
- Tim and John replaced LV board, also HCal
- safety walk-through, now back to work
- Lee and Joel worked on alarm system

MBD (Mickey)
- last wiring for interlock was done, will check if they work tomorrow
- will work on FEM next
- will need to wait for Chi for firmware update (clock master signal)

HCal (Hanpu)
- replaced LV board, now good
- MPOD bias module tripped while Eric was investigating
- now two bad modules, no spares
  - can make detector work with two good half of two half-broken modules; but this will leave us with absolutely no spares

EMCal (Sean)
- LV board replaced
- Tim investigating dark channels
  - south looking good, few issues still in north

TPOT (Hugo)
- not much to report, taking noise data, found a way to initialize board that fixes earlier problem, which is good news
- John K:  LV cables for fixing grounding ready soon, will install one today
- leave TPOT LV on-> in hands of shift crew
- will update standing orders

TPC (Jin)
- Rob signed off on cooling interlock, TPC always on, in hand of shift crew, any cooling issues contact Rob Pisani
- 96 % fo FEEs, 98 % of servers working
- trying to move to full system RC DAQ readout
- unplugged spark cable: will try after this meeting (update:  was not possible to plug in)

INTT (Rachid)
- Damon finished bias interlock cables in north, moving to south
- installing FELIX board, need Martin’s help

MVTX (Zhaozhong)
- low flow rate
- took look today, gradually decreasing, investigating, no obvious air bubble
- daq01 cooling panel was in bypass (Cameron did this to start up chiller)
- swapped some cables

sEPD (Rosi)
- fiber optics are in
- only strong back with disk is missing (wait until run has started)
- bicycle rack confirmed fit

DAQ (Martin)
- had intense weekend
- next on agenda: calorimeter read-out
- Martin partially out for training tomorrow - Thursday

Magnet (Kin)
- nothing new

Plan of the day
- DAQ development
- subsystem testing

---------------------------------------------------------------------------------
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist

Baruch:                                     BNL:
17 Lexington Ave                      Bldg. 510
office 940                                  office 2-229
phone 646-660-6272                phone 631-344-8490
----------------------------------------------------------------------------------



_______________________________________________
Sphenix-run-l mailing list
Sphenix-run-l AT lists.bnl.gov
https://urldefense.proofpoint.com/v2/url?u=https-3A__lists.bnl.gov_mailman_listinfo_sphenix-2Drun-2Dl&d=DwICAg&c=dTXc8cCP8suVpClwB1HRHQACHN4UFMgL7MtSjCbKyts&r=VpzLtnjcGB03vfJuG_p478bcDf7zDOFn2OeUM-jusdY&m=9i2YUqljNP55R0yvqQOFFqw5X4suIZ-Eznf5SUjAdUkpN_BBdCgXCLUC5q8_mzNg&s=vkUZrF0R06pA5k9fsSMKIYaP4pmmnx2n-x-FmlPL5Mw&e=


---------------------------------------------------------------------------------
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist

Baruch:                                     BNL:
17 Lexington Ave                      Bldg. 510
office 940                                  office 2-229
phone 646-660-6272                phone 631-344-8490
----------------------------------------------------------------------------------

---------------------------------------------------------------------------------
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist

Baruch:                                     BNL:
17 Lexington Ave                      Bldg. 510
office 940                                  office 2-229
phone 646-660-6272                phone 631-344-8490
----------------------------------------------------------------------------------





  • [Sphenix-run-l] Minutes shift change 2023-04-24, Stefan Bathe, 04/24/2023

Archive powered by MHonArc 2.6.24.

Top of Page