Minutes shift change 2023-04-25
general
—————
- Wednesday morning to Friday: pole tip door will be closed for test close and magnet power supply work
- no access to bore from now to Friday
- use opportunity to test all detectors together: noise, heat
- new e-log by Cameron for checking off everything that needs to be checked, almost ready to deploy
evening: Cameron
- gas mixing house phone was not connected, ITD will fix (done now)
- TPC spark cable: not safe to reattach, tied off
- FEE for TPC, high T detected, related to testing
- INTT taking pedestal data to set thresholds
night: David
- quiet
- INTT work continued until 2:00am
- ongoing low flow rate MVTX chiller
- plug door test: did not happen during night shift
day: Zhaozhong
- plug door test completed, key tree reactivated
- EMCal recovered channels: Tim
- MBD: only 2/4 flow interlock switches work (called ECW, but is air (should be fixed!), add to big screen, talked to Lee)
- investigating
- TPC 1W2 rack off today, techs working
- INTT bias interlock not working yet, Steve Boose working
- HCal temperature gui fixed
- power cycled 1W1 EMCal digitizer as per expert request
- some TPC temperatures read zero: daq error
MBD (Mickey)
- debugging FEM issues
- progress, seeing charge on analog, time channels not seen yet, investigating
- Chi back tomorrow
HCal (Hanpu)
- understand why MPOD tripped, when restart mainframe, re-initialized trip setting from 1 s to 50 ms, fixed now
- keeping bias on to monitor
- readout issue (see DAQ report)
EMCal (Sean)
- Tim made progress tracking down dark channels: all done!!!!
- test of SE preamp cooling water interlocks, OK, can leave South preamp power on (SiPMs still being worked on)
TPOT (John K)
- installed LV cables for grounding, took data, restored same noise performance as in lab
TPC (Takao)
- call regarding 1W1 work, turned off LV, back since 1:00pm, continuing monitoring FEE connectivity
- pulser data for 2/24 sectors, looking good
INTT (Jonathan)
- nothing other than bias issue already reported
MVTX (Cameron)
- tested interlocks, needs more work
- completed testing half of MVTX, moved on to next server, locked fibers, but couldn’t communicate to one of staves just now, will fix in rack
- missing fibers: ready to be shipped out, should be here tomorrow
sEPD
- nothing new
DAQ (Dan)
- two issues
- HCal: one of crate controllers isn’t interpreting Lvl1 accepts, seen this problem before in test stand, investigating
- vGTM3: all clock masters stopped working (EMCal affected), stopped locking, moved EMCal to spare ()vGTM5), seems to lock, waited for INTT to do reboot, rebooted now, vGTM3 seems to be working now
Magnet
- nothing new
Plan of the day
- when pole tip doors closed: use opportunity to test all detectors together: noise, heat
- DAQ development
- subsystem testing
-
---------------------------------------------------------------------------------
Stefan Bathe
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
_______________________________________________
Sphenix-run-l mailing list
Sphenix-run-l AT lists.bnl.gov
https://urldefense.proofpoint.com/v2/url?u=https-3A__lists.bnl.gov_mailman_listinfo_sphenix-2Drun-2Dl&d=DwICAg&c=dTXc8cCP8suVpClwB1HRHQACHN4UFMgL7MtSjCbKyts&r=VpzLtnjcGB03vfJuG_p478bcDf7zDOFn2OeUM-jusdY&m=9i2YUqljNP55R0yvqQOFFqw5X4suIZ-Eznf5SUjAdUkpN_BBdCgXCLUC5q8_mzNg&s=vkUZrF0R06pA5k9fsSMKIYaP4pmmnx2n-x-FmlPL5Mw&e=
- [Sphenix-run-l] Minutes shift change 2023-04-25, Stefan Bathe, 04/25/2023
Archive powered by MHonArc 2.6.24.