Minutes shift change 2023-04-26

general
—————
- prestart
  - still no approval
  - hopefully by May 8
  - main item is to paint the scaffolding wood with fire retardant paint  
- pole tip doors closed
  - test subsystem heat loads and noise levels
  - magnet test
  - plan is to open doors Friday morning
- yesterday’s RHIC planning meeting
  - calendar  
    - May 8 begin cool down (cryo weeks start counting = budget starts counting)
    - May 10 beam in blue ring, beginning of no access
    - May 16 evening store for experiments
    - May 18 sPHENIX solenoid at 4 K, two days of restricted access/controlled access
  - run length:  20 cryo weeks (to last week of September)
    - cosmics running after run ends:  solenoid off (need cryo for solenoid)


evening:  Genki
- quiet
- gas cylinder for TPOT replaced by Rob at 5:30
- activity for MVTX

night:  David
- quiet
- MVTX chilldyne cooler flow back up to 10.8 l/min
- at 7:30 work on rack 1W2

day:  Zhaozhong
- pole tip doors closed at noon
- TPC LV off at 8:00am for cooling work, restored at 2:00pm
- CAD did ODH test, exhaust fan on, access:  safety access

MBD (Mickey)
- didn’t have a chance to test interlocks
- can see laser now, but still investigating

HCal (Hanpu)
- can read out detector again, but no signal from 2W2 lower, only pedestal

EMCal
- no report

TPOT (Hugo, John K)
- nothing new

TPC (Takao)
- LV on now
- John and Jin are working on taking data on RC DAQ

INTT (Genki)
- installed FELIX boards to DAQ servers, waiting for preparation of DAQ

MVTX (Cameron)
- system tested 5/6 felix servers, all problems addressed, started testing 6th, all fiber connections good, cannot access one stave, one connector damaged, fixed, but still communication problem with that stave
- cooling: high T readout: no water, crack in hose, replaced, all good
- LC fibers snapped, swapped in unused fiber, all god
- connected MTT fibers
- global system tests will start tomorrow

sEPD
- no report

DAQ (Dan, John K)
John K:  GTM fibers restored, TPC
Dan:  trouble shooting manual
 with Joey investigating event FFFF in beginning of digitizer runs

Magnet (Kin)
- Pablo Rosa working on magnet power supply this afternoon and tomorrow

Plan of the day
- take data with subsystems individually (if possible) with all detectors having LV on (if safe) to look at noise and temperature
---------------------------------------------------------------------------------
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist

Baruch:                                     BNL:
17 Lexington Ave                      Bldg. 510
office 940                                  office 2-229
phone 646-660-6272                phone 631-344-8490
----------------------------------------------------------------------------------



_______________________________________________
Sphenix-run-l mailing list
Sphenix-run-l AT lists.bnl.gov
https://urldefense.proofpoint.com/v2/url?u=https-3A__lists.bnl.gov_mailman_listinfo_sphenix-2Drun-2Dl&d=DwICAg&c=dTXc8cCP8suVpClwB1HRHQACHN4UFMgL7MtSjCbKyts&r=VpzLtnjcGB03vfJuG_p478bcDf7zDOFn2OeUM-jusdY&m=9i2YUqljNP55R0yvqQOFFqw5X4suIZ-Eznf5SUjAdUkpN_BBdCgXCLUC5q8_mzNg&s=vkUZrF0R06pA5k9fsSMKIYaP4pmmnx2n-x-FmlPL5Mw&e=



  • [Sphenix-run-l] Minutes shift change 2023-04-26, Stefan Bathe, 04/26/2023

Archive powered by MHonArc 2.6.24.

Top of Page