Hello All,

The first full maintenance day is delayed from June 14 to June 21.  See below.

Regards,
Stefan

---------------------------------------------------------------------------------
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist

Baruch:                                     BNL:
17 Lexington Ave                      Bldg. 510
office 940                                  office 2-229
phone 646-660-6272                phone 631-344-8490
----------------------------------------------------------------------------------



Begin forwarded message:

From: "Lovelace III, Henry" <hlovelace AT bnl.gov>
Subject: APEX and Maintenance schedule Starting June 7th
Date: May 23, 2023 at 15:46:08 EDT
To: "Bathe, Stefan" <bathe AT bnl.gov>, "Lee, Jeong-Hun" <jhlee AT bnl.gov>
Cc: "Dunlop, James C" <dunlop AT bnl.gov>, "Shrey, Travis C" <shrey AT bnl.gov>, "Luo, Yun" <yluo AT bnl.gov>, "Sampson, Paul" <sampson AT bnl.gov>, "Minty, Michiko" <minty AT bnl.gov>, "Fischer, Wolfram" <wfischer AT bnl.gov>

* This email originates from a sender outside of CUNY. Verify the sender before replying or clicking on links and attachments. *
Hi,
   Below is the proposed APEX and maintenance schedule for June and July.

  • 6/07/23 APEX
  • 6/14/23 APEX
  • 6/21/23 Maintenance
  • 6/28/23 APEX
  • 7/5/23 Maintenance
  • 7/12/23 APEX
  • 7/19/23 Maintenance
  • 7/26/23 APEX


Cheers,
Henry

(631) 344-5605 (Office)
(757) 879-3915 (Cell)

Collider - Accelerator Department
Electron-Ion Collider Accelerator Design

"To do my best, and let that stand the record of my brain and hand..."



  • [Sphenix-run-l] Fwd: APEX and Maintenance schedule Starting June 7th, Stefan Bathe, 05/23/2023

Archive powered by MHonArc 2.6.24.

Top of Page