From: Fischer, Wolfram <wfischer AT bnl.gov>
Dear sPHENIX and STAR experimenters,
attached please find an update of the RHIC projections. The latest version of this document is always posted here: https://www.rhichome.bnl.gov/RHIC/Runs/RhicProjections.pdf
For p+p, the delivered luminosity for different crossing angles and vertex regions is stated Table 2. To deliver ~75 pb^-1 to sPHENIX in +-10 cm will take approximately 20 weeks without any improvements over Run-15.
Please distribute as needed, and let me know if you need any further information.
Wolfram and Kiel
From:
"Fischer, Wolfram" <wfischer AT bnl.gov>
Dear sPHENIX and STAR experimenters,
attached please find an update of the RHIC projections. The latest version of this document is always posted here: https://www.rhichome.bnl.gov/RHIC/Runs/RhicProjections.pdf
For p+p, in light of this year’s run experience (even without all the AC problems), we cannot count on exceeding the Run-15 performance. This is now almost a decade ago and we did not have too much practice since Run-15. p+p is, however, less affected by the SEY de-conditioning we have seen with Au+Au.
The impact of the early termination of Run-23 is not yet fully reflected in the document in case a Au+Au mode is added.
Please distribute as needed, and let me know if you need any further information.
Wolfram