  • Subject: [Sphenix-run-l] Work in ODH Service Buildings - 1002B, 1004B, 1006B, 1008B, 1010A and 1012A.
  • Date: Thu, 21 Dec 2023 15:57:27 +0000

Just another reminder for the ODH works (installing light/alarm for the service buildings).

 

Hopefully, it’ll not affect us.  But since it’s “tests”, something can go wrong.

 

Today, the “Access” 1008-IR will be changed to “safe mode” when the Access Control Group comes down to do the test.  It may be half an hour or so in that state.   This “safe mode” is only the case for today, NOT every day. 

 

Kin

 

From: Hillis, Darren <dhillis AT bnl.gov>
Sent: Thursday, December 21, 2023 10:49 AM
To: Yip, Kin <kinyip AT bnl.gov>; Sampson, Paul <sampson AT bnl.gov>; Marr, Gregory <gmarr AT bnl.gov>; Bathe, Stefan <bathe AT bnl.gov>; Vasquez, Joel <jvasquez AT bnl.gov>; Reich, Jonathan <reich AT bnl.gov>; Toldo, Frank A <fatoldo AT bnl.gov>; Pisani, Robert <pisani AT bnl.gov>; Albanese, Marianna <malbanese AT bnl.gov>
Cc: Access Controls Group <accesscontrols AT bnl.gov>; Reich, Jonathan <reich AT bnl.gov>; Benante, John T <benante AT bnl.gov>; Giorgio, Caitlin <charper AT bnl.gov>; Fliller, Raymond <rfliller AT bnl.gov>; Craner, Francis <fcraner AT bnl.gov>
Subject: Work in ODH Service Buildings - 1002B, 1004B, 1006B, 1008B, 1010A and 1012A.

 

All,

 

I apologize for not specifically today calling, before the trip at 1006B.

 

Access Controls Technicians will be working in 1002B, 1004B, 1006B, 1008B, 1010A and 1012A and powering up components for the next month plus every day for the new ODH Indicators. There is not an anticipate effect on mode, ODH alarms or any functions within 1008IR, but there is always this possibility when work is being performed. If we know something happen on our end we will call to inform.

 

I will also call all the following, every morning for the next month, as well as in the afternoon when shift changes:

             Notify sPHENIX Control Room Shift Supervisor at x7815

Notify 911MCR Control Room Personnel at x4662

Notify CAS Support at x2024

            Notify Kin Yip @ x 4116

            Notify Frank Toldo @ x7788

 

Thanks,

 

 

Darren Hillis

Access Controls Group

Collider-Accelerator Department

Brookhaven National Laboratory

Upton, NY 11973 USA

W(631)344-5849

Cell(631)742-5081

dhillis AT bnl.gov

 



  • [Sphenix-run-l] Work in ODH Service Buildings - 1002B, 1004B, 1006B, 1008B, 1010A and 1012A., Yip, Kin, 12/21/2023

Archive powered by MHonArc 2.6.24.

Top of Page