sphenix-run-l AT lists.bnl.gov
Subject: Commissioning and running of sPHENIX
List archive
[Sphenix-run-l] FW: 1008 Automatic Transfer Switch Test- 2/6/2024 9:30am
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "sphenix-run-l AT lists.bnl.gov" <sphenix-run-l AT lists.bnl.gov>, "Rau, Michael" <mrau AT bnl.gov>, "Toldo, Frank A" <fatoldo AT bnl.gov>
- Subject: [Sphenix-run-l] FW: 1008 Automatic Transfer Switch Test- 2/6/2024 9:30am
- Date: Mon, 5 Feb 2024 14:32:59 +0000
Hello,
Upon our request, PK Feng and the C-AD Power Distribution group have agreed to move the “transfer” test to 9:30 am.
It seems that they’re eager to do the “transfer” test as soon as possible.
Typically, we won’t have interruption as we have UPS. Here they’re talking about those systems (like the Cryo Group’s Air Compressors in 1008B) which don’t have UPS protection.
Kin
From: Trent, Herbie <htrent AT bnl.gov>
Hello Kin,
Yes, we will move the test to 9:30am tomorrow morning.
Regards,
Herbie Trent Electrical Supervisor
Brookhaven National Laboratory Collider-Accelerator Department Building 912, Room S-10 Upton, NY 11973-5000 Office: 631- 344- 8046 Mobile: 631-764-6588 Email: htrent AT bnl.gov
-------- Original message -------- From: "Yip, Kin" <kinyip AT bnl.gov> Date: 2/5/24 9:14 AM (GMT-05:00) To: "Trent, Herbie" <htrent AT bnl.gov> Cc: "McKay, Robert" <mckayb AT bnl.gov>, Fire Alarm Shop <firealarmshop AT bnl.gov>, "Feng, Pei Kuan" <pkfeng AT bnl.gov> Subject: RE: 1008 Automatic Transfer Switch Test- 2/6/2024 10:30am
Hello,
Can you please do the test at 9:30am ?
We are worried about any problem. It'll be good that we don't need to stop in the middle of our work. Due to meeting, our works don't usually start before 9:30 am.
Kin
-------- Original message -------- From: "Trent, Herbie" <htrent AT bnl.gov> Date: 2/2/24 16:58 (GMT-05:00) To: CAD Personnel List <allcad AT bnl.gov> Cc: "McKay, Robert" <mckayb AT bnl.gov>, Fire Captains <FireCaptains AT bnl.gov>, Fire Alarm Shop <firealarmshop AT bnl.gov>, "Yip, Kin" <kinyip AT bnl.gov> Subject: 1008 Automatic Transfer Switch Test- 2/6/2024 10:30am
Please be advised that on Tuesday 2/6/2024 we will be performing the monthly transfer test for 1008 at 10:30am.
Areas affected: 1008A, 1008B, Alcove 7C, Alcove 9A and Alcove 9B
Only systems on N/E power will be affected. Expect a 10-20 second power interruption at the beginning and conclusion of this test.
Please contact Herbie Trent x8046 for concerns.
|
- [Sphenix-run-l] FW: 1008 Automatic Transfer Switch Test- 2/6/2024 9:30am, Yip, Kin, 02/05/2024
Archive powered by MHonArc 2.6.24.