Subject: Commissioning and running of sPHENIX
List archive
[[Sphenix-run-l] ] 28x28-bunched fill GEM stability test run report
- From: "Huang, Jin" <jhuang AT bnl.gov>
- To: "sphenix-tpc-l AT lists.bnl.gov" <sphenix-tpc-l AT lists.bnl.gov>
- Cc: "sphenix-tracking-l AT lists.bnl.gov" <sphenix-tracking-l AT lists.bnl.gov>, "sphenix-tracking-l AT lists.bnl.gov" <sphenix-tracking-l AT lists.bnl.gov>, "sphenix-run-l AT lists.bnl.gov" <sphenix-run-l AT lists.bnl.gov>
- Subject: [[Sphenix-run-l] ] 28x28-bunched fill GEM stability test run report
- Date: Sat, 3 Aug 2024 04:13:28 +0000
______________________________
Jin HUANG
Physicist, Ph.D.
Brookhaven National Laboratory
Physics Department, Bldg 510 C
Upton, NY 11973-5000
Office: 631-344-5898
Cell: 757-604-9946
______________________________
Sent: Wednesday, July 31, 2024 12:03 AM
To: sphenix-tpc-l AT lists.bnl.gov <sphenix-tpc-l AT lists.bnl.gov>
Cc: sphenix-tracking-l AT lists.bnl.gov <sphenix-tracking-l AT lists.bnl.gov>; sphenix-tracking-l AT lists.bnl.gov <sphenix-tracking-l AT lists.bnl.gov>; sphenix-run-l AT lists.bnl.gov <sphenix-run-l AT lists.bnl.gov>
Subject: TPC gain measurement with beam in tracking meeting Wed 11AM
Cheers
______________________________
Jin HUANG
Physicist, Ph.D.
Brookhaven National Laboratory
Physics Department, Bldg 510 C
Upton, NY 11973-5000
Office: 631-344-5898
Cell: 757-604-9946
______________________________
Sent: Monday, July 29, 2024 4:18 PM
To: sphenix-tpc-l AT lists.bnl.gov <sphenix-tpc-l AT lists.bnl.gov>
Cc: sphenix-tracking-l AT lists.bnl.gov <sphenix-tracking-l AT lists.bnl.gov>; sphenix-tracking-l AT lists.bnl.gov <sphenix-tracking-l AT lists.bnl.gov>; sphenix-run-l AT lists.bnl.gov <sphenix-run-l AT lists.bnl.gov>
Subject: Special TPC meeting on cosmic data review, Tue July 30 9:30AM.
-
Live action at https://chat.sdcc.bnl.gov/sphenix/channels/tpc-electronics
______________________________
Jin HUANG
Physicist, Ph.D.
Brookhaven National Laboratory
Physics Department, Bldg 510 C
Upton, NY 11973-5000
Office: 631-344-5898
Cell: 757-604-9946
______________________________
-
[[Sphenix-run-l] ] 28x28-bunched fill GEM stability test run report,
Huang, Jin, 08/03/2024
-
[[Sphenix-run-l] ] 56x56-bunched fill GEM stability test run report,
Huang, Jin, 08/05/2024
-
[[Sphenix-run-l] ] 111x111-bunched fill GEM stability test run report,
Huang, Jin, 08/09/2024
- Re: [[Sphenix-run-l] ] 111x111-bunched fill GEM stability test run report, David Morrison, 08/10/2024
-
[[Sphenix-run-l] ] Aug-11 run report,
Huang, Jin, 08/12/2024
-
[[Sphenix-run-l] ] Aug-13 run report,
Huang, Jin, 08/13/2024
-
[[Sphenix-run-l] ] Overnight physics run test report,
Huang, Jin, 08/14/2024
-
[[Sphenix-run-l] ] Zero suppression tuning run report, Aug-15,
Huang, Jin, 08/16/2024
- [[Sphenix-run-l] ] Beam time use report for data pipeline performance tuning, Aug-15, Huang, Jin, 08/21/2024
-
[[Sphenix-run-l] ] Zero suppression tuning run report, Aug-15,
Huang, Jin, 08/16/2024
-
[[Sphenix-run-l] ] Overnight physics run test report,
Huang, Jin, 08/14/2024
-
[[Sphenix-run-l] ] Aug-13 run report,
Huang, Jin, 08/13/2024
- Re: [[Sphenix-run-l] ] 111x111-bunched fill GEM stability test run report, Xiaochun He, 08/16/2024
-
[[Sphenix-run-l] ] 111x111-bunched fill GEM stability test run report,
Huang, Jin, 08/09/2024
-
[[Sphenix-run-l] ] 56x56-bunched fill GEM stability test run report,
Huang, Jin, 08/05/2024
Archive powered by MHonArc 2.6.24.