[[Sphenix-run-l] ] 10 phones replaced in 1008 and pressure test for the heat exchanger was completed successfully at the 3rd of IR8
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "sphenix-run-l AT lists.bnl.gov" <sphenix-run-l AT lists.bnl.gov>
- Subject: [[Sphenix-run-l] ] 10 phones replaced in 1008 and pressure test for the heat exchanger was completed successfully at the 3rd of IR8
- Date: Fri, 6 Dec 2024 21:54:44 +0000
Hello,
We have replaced 10 new phones in 1008 that work with the Lab.'s new phone system. I replaced 4 desktop phones myself and the ITD tech.
replaced those that are wall-mounted. I quickly tested all of them and only 1 didn't work. I called ITD a couple hours ago and they promised to
fix it (or it might have been fixed by now ... related to MAC address). Most importantly, the phone nos. for the 3 phones in the Control Room are
still x7821, x7815 and x8360.
{ Interestingly, a couple C-AD MCR operators came to check earlier today whether our phones work to communicate with MCR. }
Below is a message from the Cryo group which just completed the pressure test for the new heat exchanger . But they will wait until Monday to start
the LN2 cooling for the sPHENIX Magnet.
Kin
-------- Forwarded Message --------
Subject: | Re: Pressure test on L3 of sPhenix at 14:30 (2:30) today |
---|---|
Date: | Fri, 6 Dec 2024 21:07:12 +0000 |
From: | Riker, Kenneth D <kenr AT bnl.gov> |
To: | Toldo, Frank A <fatoldo AT bnl.gov>, Warkentien, Andreas F <andyw AT bnl.gov>, Weissman, Andrew <aweissman AT bnl.gov>, Feder, Russell <rfeder AT bnl.gov>, Martin, Daniel <martin AT bnl.gov>, Stivala, Nicholas <stivala AT bnl.gov>, Sheth, Chintan <csheth AT bnl.gov>, Than, Yatming (Roberto) <ythan AT bnl.gov>, Yip, Kin <kinyip AT bnl.gov> |
Sent: Friday, December 6, 2024 1:06:41 PM
To: Toldo, Frank A <fatoldo AT bnl.gov>; Warkentien, Andreas F <andyw AT bnl.gov>; Weissman, Andrew <aweissman AT bnl.gov>; Feder, Russell <rfeder AT bnl.gov>; Martin, Daniel <martin AT bnl.gov>; Stivala, Nicholas <stivala AT bnl.gov>; Sheth, Chintan <csheth AT bnl.gov>; Than, Yatming (Roberto) <ythan AT bnl.gov>; Yip, Kin <kinyip AT bnl.gov>
Subject: Pressure test on L3 of sPhenix at 14:30 (2:30) today
Technical Associate I Mechanical
Cryo Mechanical Technicians,
Collider Accelerator Department
Office: 631.344.3172 | Mobile: 631.252.2844
kenr AT bnl.gov
𝕏 | Facebook | Instagram | LinkedIn
- [[Sphenix-run-l] ] 10 phones replaced in 1008 and pressure test for the heat exchanger was completed successfully at the 3rd of IR8, Yip, Kin, 12/06/2024
Archive powered by MHonArc 2.6.24.