  • From: Zhenyu Ye <yezhenyu2003 AT gmail.com>
  • To: Yi Yang <yiyang AT ncku.edu.tw>
  • Cc: star-fst-l AT lists.bnl.gov
  • Subject: Re: [Star-fst-l] impact from corona virus
  • Date: Tue, 24 Mar 2020 04:07:35 -0500



> On Mar 18, 2020, at 12:21 AM, Yi Yang <yiyang AT ncku.edu.tw> wrote:
>
> Dear all,
>
> Elke asked about the impact on FST from corona virus and I mentioned four
> major components in the meeting. Please find the summary below and feel
> free to add what I missed:
>
> - Sensor: we need to check with Hamamatsu, but we only expect to (hope)
> have small impact. (Zhenyu)

Reply from Hamamatsu: We've not so far been affected by covid-19; however,
considering the uncertainties surrounding this situation, we recommend to all
customers to place any upcoming orders as soon as possible so that material
procurements and other preparatory steps for their purchases can begin in
earnest. The sooner an order is booked, the sooner the production work for it
can begin, and that can be very helpful in these uncertain times…

>
> - Mechanical structure: NCKU will be closed if we have one more confirmed
> case (just got the first one yesterday). However, the main parts are made
> by private companies (AIDC and Easton), so the impact should be small. (Yi)
>
> - Hybrid PCB/T-Board: the impact will be large if the design needs to be
> modified since Jianing and Maowu probably can not go back to campus anytime
> soon. The production also might be delayed. Jianing should provide more
> information to us. (Jianing)
>
> - Connectors: we should place the order asap if we won't change the
> connector since the situation in France is not optimistic. One possibility
> is to do it through Taiwan's agent, but I don't have budget to do it. We
> need to make decision soon. (Zhenyu, Flemming, Jianing, Yi)

I would like to understand whether or not we need to order connectors fro
prototype modules. Yi, can you please remind me how many connectors for
hybrid you have in hand?

I also would like to decide on when/how to order the connectors for the
production. We need to assemble around 48 modules, where each module with two
sets of connectors, and each set includes one A22-2-T-34-V22 for T-board
assembly by BNL, and one A22-1-T-34-V16 for hybrid assembly by NCKU. I think
perhaps we should order something around 120 sets. Since NCKU does not have
the funds, can BNL purchase all these connectors?

Zhenyu

>
> Cheers,
> Yi
>
> +++++++++++++++++++++++++++++++++++++++++++++++++++
> Yi Yang, Associate Professor
> Department of Physics
> National Cheng Kung University
> Tainan, 701 Taiwan
> E-Mail: yiyang AT ncku.edu.tw
> Tel: +886-6-2757575 ext.65237
> Fax: +886-6-2747995
> Group Web:
> https://urldefense.com/v3/__http://phys.ncku.edu.tw/*yiyang__;fg!!P4SdNyxKAPE!TpXQgkTdsKBtj9zGa-Tz65NmVph-Rtod9kSrzEeC6QmugUMgBixtTwDOc8OR3pYLjnLOQtM$
>
> +++++++++++++++++++++++++++++++++++++++++++++++++++
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l





Archive powered by MHonArc 2.6.24.

Top of Page