Hi,
There had to be some additional joggling with dates due to people's availability; It seems the review is settled fo Monday 8/3. The reviewers will be, all from BNL
Jim Stewart
Jim Mills
Gerrit van Nieuwenhuizen
Paul o’Connor
Grezgor Deptuch
And the proposed agenda
Introduction -> Zhenyu Ye (15’)
Detector requirements
Design conceptsModule
Mechanical production -> Yi Yang (25’)
Hybrids
Mechanical sector production
Assembly
Tests and QA
Hybrid production and QC – Maowu (15’)
Prototype module assembly and performance
- Xu Sun (25’)
Module assembly at FNAL
Tests and QA at UIC (procedures)
Performance from the tests
Performance in simulation based on the measured response
Mechanical integration -> Rahul Sharma (25’)
Requirements,
Design
Support structures
Detector support interface
Cooling system
-> Summary and Outlook - Flemming Videbaek (25’)
Electronics, DAQ and Slow Control
Schedule, Milestones, Resources
We will discuss this more at tomorrows meeting
best Flemming
--
Flemming Videbaek
senior scientist
videbaek @ bnl.gov
Brookhaven National Lab
Physics Department
Bldg 510D
Upton, NY 11973
phone: 631-344-4106
cell : 631-681-1596
-
[Star-fst-l] production readiness review date,
videbaek, 07/19/2020
-
Re: [Star-fst-l] production readiness review date,
Zhenyu Ye, 07/21/2020
- Re: [Star-fst-l] production readiness review date, Yi Yang, 07/21/2020
-
Re: [Star-fst-l] production readiness review date,
Zhenyu Ye, 07/21/2020
Archive powered by MHonArc 2.6.24.